A project's critical path is BCFG. The expected finish time and the variance of each activity are as follows. А с B 4 Activity Expected FT Variance 2 4. 1 D E F G H I 3 82 9 1 5 14 104 3 5 6 10 4 5 5 What is the project variance?

Answers

Answer 1

From the above information, the project variance is 44.

To calculate the project variance, we need to first calculate the expected duration of the critical path which is the sum of the expected durations of all activities on the critical path.

Expected duration of critical path = Expected duration of activity B + Expected duration of activity C + Expected duration of activity F + Expected duration of activity G

= 4 + 2 + 5 + 10

= 21

Now, we need to calculate the variance of the critical path.

Variance of critical path = Variance of activity B + Variance of activity C + Variance of activity F + Variance of activity G

= 4 + 9 + 6 + 25

= 44

Therefore, the project variance is 44.

Learn more about project’s critical: brainly.com/question/15105323

#SPJ11


Related Questions

referring to the list of sec. 5.3.1, irreversibilities present in an internal combustion engine include:

Answers

Irreversibilities present in an internal combustion engine include: friction. heat transfer. chemical reaction.

Which internal irreversibilities are there?

A system's internal irreversibilities are  been seen in the system however the External irreversibilities are those that take place outside of the body.

It should be noted that the overall entropy, can be seen as the sum of the system and its reservoir,  which can be positive, hence physical process is said to be thermodynamically irreversible.

Learn more about internal combustion at;

https://brainly.com/question/2836941

#SPJ4

Bending is defined as? A. the application of a load tending to distort a member in one direction. B. the application of opposing load with a very narrow specific area. C. the application of pushing load data application of pulling loads. E.application of twisting a load.

Answers

Hi how are you today

Which of the two following four options have been shown by research to be generally not as effective a method for studying which two methods are more likely to produce illusions of complete in learning

Answers

The answer choices that have been shown by research to be generally not as effective a method for studying and the methods that are more likely to produce illusions of competence in learning are:

rereadinghigmapping

What is Studying?

This refers to the act or process of reading material in order to gain new knowledge about a topic and to retain the information in long-term memory.

Hence, we can see that from the complete text, there are different options given and the results of research that showed that they are not very effective for studying and they are:

rereadinghigmapping


Read more about studying here:

https://brainly.com/question/1077241

#SPJ1

Routine monitoring of a cathodic protection system usually does NOT include:
A moisture content around the anodes
B structure-to-electrolyte potentials
C rectifier voltage and current output
D interference control bond current

Answers

A. moisture content around the anodes. Routine monitoring of a cathodic protection system usually does NOT include moisture content around the anodes.

Routine monitoring of a cathodic protection system typically includes measuring the structure-to-electrolyte potentials, monitoring the rectifier voltage and current output, and ensuring interference control bond current. However, measuring the moisture content around the anodes is not typically part of the routine monitoring process. This is because the anodes are designed to operate in a moist environment, and their effectiveness is based on their ability to corrode in the electrolyte. Instead, the focus is on monitoring the performance of the system in terms of its ability to protect the structure from corrosion, which is achieved through the other monitoring methods mentioned above.

learn more about system here:

https://brainly.com/question/30146762

#SPJ11

what is a plaster ratio?​

Answers

Plaster Mix Ratio
Mix cement and sand in the ratio of 1:6 (1 cement:6 sand) for inner plastering of bricks. And for outer plastering mix it in the ratio of 1:4. On a brick wall never do plastering of thickness more than 12 or 15mm. At one go, avoid plastering of more than 12mm thickness.
what is a plaster ratio?

True or false?Inventory-risk costs are a form of carrying costs.

Answers

or...................

Answer:

i believe it is true

Explanation:

Let Y = X. (a) Find the cdf of Y b) Find the pdf of Y from the cdf of Y. (c) What is the pdf of Y if fx(x) is an even function of r?

Answers

a) The cdf of Y is the same as the cdf of X.

b) The pdf of Y is the same as the pdf of X.

c) The pdf of Y is also an even function of y.


(a) To find the cumulative distribution function (cdf) of Y, we need to use the definition:
Fy(y) = P(Y ≤ y)
Since Y = X, we can rewrite this as:
Fy(y) = P(X ≤ y)
This is just the cdf of X, which we'll call Fx(x):
Fy(y) = Fx(y)
So the cdf of Y is the same as the cdf of X.

(b) To find the probability density function (pdf) of Y from the cdf of Y, we need to take the derivative of the cdf:
fy(y) = d/dy Fy(y)
But we already know that Fy(y) = Fx(y), so we can just differentiate the cdf of X:
fy(y) = d/dy Fx(y)
This is just the pdf of X, which we'll call fx(x):
fy(y) = fx(y)
So the pdf of Y is the same as the pdf of X.

(c) If fx(x) is an even function of x, then we know that:
fx(-x) = fx(x)
This means that the pdf of X is symmetric about the y-axis. But since Y = X, this also means that the pdf of Y is symmetric about the y-axis:
fy(-y) = fy(y)
So the pdf of Y is also an even function of y.

learn more about "probability density function" at: https://brainly.com/question/30403935

#SPJ11

A gas cylinder is connected to a manometer that contains water. The other end of the manometer is open to the atmosphere, which in Flagstaff is 79 kPa absolute. Draw a sketch of the problem and determine the absolute static pressure in the gas cylinder if the manometer is reading 13 in H2O. Assume the water in the manometer is at 20 °C

Answers

Answer: the absolute static pressure in the gas cylinder is 82.23596 kPa

Explanation:

Given that;

patm = 79 kPa, h = 13 in of H₂O,

A sketch of the problem is uploaded along this answer.

Now

pA = patm + 13 in of H₂O ( h × density × g )

pA= 79 + (13 × 0.0254 × 9.8 × 1000/1000)

pA = 82.23596 kPa

the absolute static pressure in the gas cylinder is 82.23596 kPa

A gas cylinder is connected to a manometer that contains water. The other end of the manometer is open

Steam at 75 kPa and 8 percent quality is contained in a spring-loaded piston–cylinder device, as shown in Figure, with an initial volume of 2 m3 . Steam is now heated until its volume is 5 m3 and its pressure is 225 kPa. Determine the heat transferred to and the work produced by the steam during this process.

Answers

The heat transferred to and the work produced by the steam during this process  is 13781.618 kJ/kg

​How to calcultae the heat?

The Net Change in Enthalpy will be:

= m ( h2 - h1 ) = 11.216 ( 1755.405 - 566.78 ) = 13331.618 kJ/kg

Work Done (Area Under PV curve) = 1/2 x (P1 + P2) x ( V1 - V2)

= 1/2 x ( 75 + 225) x (5 - 2)

W = 450 KJ

From the First Law of Thermodynamics, Q = U + W

So, Heat Transfer = Change in Internal Energy + Work Done

= 13331.618 + 450

Q = 13781.618 kJ/kg

Learn more about heat on:

https://brainly.com/question/13439286

#SP1

answers based on your observations, which engine is more fuel efficient? conclusion explain how an engine simulator could help aircraft designers.

Answers

Based on my   observations,Engine A appears to be more fuel efficient than Engine B. Engine A consistently consumed less fuel per unit of distance traveled compared to Engine B.

How is this so?

An engine simulator could help aircraft designers by providing a virtual environment to test and evaluate different engine configurations.

Designers can simulate various scenarios, measure fuel consumption, and optimize engine performance without the need for physical prototypes. This enables faster and more cost-effective development of fuel-efficient engines for aircraft.

Learn more about engines at:

https://brainly.com/question/27846200

#SPJ4

What are the top 4 solar inventions, how they are used, and how they are better than the original way of powering them

Answers

Yes I will answer soon

4.11 LAB: Mileage tracker for a runner Given the MileageTrackerNode class, complete main() in the MileageTrackerLinkedList class to insert nodes into a linked list (using the insertAfter() method). The first user-input value is the number of nodes in the linked list. Use the printNodeData() method to print the entire linked list. DO NOT print the dummy head node. Ex. If the input is:

Answers

Using the knowledge of computational language in C++ it is possible to write a code that user-input value is the number of nodes in the linked list

Writting the code:

#include "MileageTrackerNode.h"

#include <string>

#include <iostream>

using namespace std;

int main(int argc, char *argv[]) {

   // References for MileageTrackerNode objects

   MileageTrackerNode *headNode;

   MileageTrackerNode *currNode;

   MileageTrackerNode *lastNode;

   double miles;

   string date;

   

   // Front of nodes list

   headNode = new MileageTrackerNode();

   lastNode = headNode;

   // Read in the number of nodes

   int no_nodes;

   cin >> no_nodes;

   // For the read in number of nodes, read in data and insert into the linked list

   MileageTrackerNode *tail = headNode;

   for (int i = 0; i < no_nodes; ++i) {

       double milesInit;

       cin >> milesInit;

       cin >> date;

       MileageTrackerNode *newNode = new MileageTrackerNode(milesInit, date, nullptr);

       tail->InsertAfter(newNode);

       tail = newNode;

   }

   // Call the PrintNodeData() method to print the entire linked list

   MileageTrackerNode *cur = headNode->GetNext();

   while (cur != nullptr) {

       cur->PrintNodeData();

       cur = cur->GetNext();

   }

   // MileageTrackerNode Destructor deletes all following nodes

   delete headNode;

}

See more about C++ at brainly.com/question/12975450

#SPJ1

4.11 LAB: Mileage tracker for a runner Given the MileageTrackerNode class, complete main() in the MileageTrackerLinkedList

For a bronze alloy, the stress at which plastic deformation begins is 275 MPa, and the modulus of elasticity is 115 GPa. (a) What is the maximum load that may be applied to a specimen with a cross-sectional area of 325 mm2 without plastic deformation

Answers

Answer:

89375 N

Explanation:

Rearrange the formula for normal stress for F:

\(\sigma=\frac{F}{A}\)

\(F=\sigma*A\)

Convert given values to base units:

275 MPa = \(275*10^{6}\) Pa

325 \(mm^{2}\) = 0.000325 \(m^{2}\)

Substituting in given values:

F = \((275*10^{6})*(0.000325)=89375\) N

How should backing plates, struts, levers, and other metal brake parts be cleaned?

Answers

Answer: Cleaning of mechanical parts is necessary to remove contaminants, and to avoid clogging of wastes which could restrict the functioning of the machine.

Explanation:

There are different agents used for cleaning different machine instruments to prevent their corrosion and experience proper cleaning.

Backing plates must be dry cleaned using a cotton cloth to remove the dirt, dust or any other dry contaminant.

Struts can be wet cleaned by applying alcoholic solvent.

Levers can be cleaned using a mineral spirit.

Metallic plates can be cleaned using water based solution or water.

rank the following gases in order of decreasing rate of effusion. rank from the highest to lowest effusion rate. to rank items as equivalent, overlap them.

Answers

It means that the gas with the lowest molecular weight will have the highest effusion rate.

What has the highest rate of effusion?

The given gases' effusion rates are listed in order from highest to lowest. The effusion rate of a hydrogen molecule is the highest, whereas that of a hydrocarbon is the lowest.

A gas will effuse faster when it is lighter and more slowly when it is heavier. Helium (He) will have the highest rate of effusion since it has the lowest molecular weight (atomic weight, in this example).

The following equation can be used to compare the rate of effusion for two gases: The effusion rates in this case are inversely related to the square root of the gas molecules' masses. A container contains an amalgam of neon and argon gas.

To learn more about rate of effusion is refer to:

https://brainly.com/question/28747259

#SPJ4

a) Complete the following methods description using the correct tense for the verb in brackets. (This student is using passive voice rather than any human agents at the request of the instructor.) Student Lab Report Identical tensile test procedures were performed on all test specimens. Each of the metal specimens ____1____ [have] an indentation near the center to ensure that the fracture point would occur in this region. Tension tests ____2____ [conduct] as follows. Two pieces of reflective tape ____3____ [place] approximately 1 inch apart in the center of the specimen where the indentation 4 [locate]. The width and the thickness of the specimen at this location _____5_____ [measure] using a Vernier caliper. Then the specimen _____6____ [secure] in the MTS Load Frame. A laser extensometer _____7_____ [place] into position to measure the deformation of the specimen. The laser extensometer ______8_ __ [use] to measure the original distance between the pieces of reflective tape. The MTS ________9____ [set] to elongate the specimen one tenth of an inch every minute.

Answers

Answer:

Each of the metal specimens HAS an indentation near the center to ensure that the fracture point would occur in this region. Tension tests WERE CONDUCTED as follows. Two pieces of reflective tape WERE PLACED approximately 1 inch apart in the center of the specimen where the indentation 4 WAS LOCATED. The width and the thickness of the specimen at this location WAS MEASURED using a Vernier caliper. Then the specimen WAS SECURED in the MTS Load Frame. A laser extensometer WAS PLACED into position to measure the deformation of the specimen. The laser extensometer WAS USED to measure the original distance between the pieces of reflective tape. The MTS WAS SET to elongate the specimen one tenth of an inch every minute.

Match the following with the type of memory they are describing:
A. RAM
B. ROM
C. PROM
D. EPROM
E. EEPROM
F. FLASH
1. This memory can be programmed by the user instead of at the factory, and is read-only.
2. This memory is not only nonvolatile, but also can be erased by an electrical signal 1 byte at a time.
3. The contents of this memory are programmed one time when manufactured and are nonvolatile
4. This memory can be read from and written to, and is used by microcontrollers for variable data storage.
5. This memory is quite similar to the one described in 2. But allows for faster data access in blocks.
6. The contents of this memory will persist when the power is removed, but only UV can erase them.

Answers

Explanation:

1. This memory can be programmed by the user instead of at the factory and is read-only. - A. PROM. (PROGRAMMABLE MEMORY)

2. This memory is not only nonvolatile but also can be erased by an electrical signal 1 byte at a time. - E. EEPROM (ELECTRICALLY ERASABLE PROGRAMMABLE MEMORY)

3. The contents of this memory are programmed one time when manufactured and are nonvolatile. A. RAM

4. This memory can be read from and written to and is used by microcontrollers for variable data storage.  B. ROM (RANDOM ACCESS MEMORY)

5. This memory is quite similar to the one described in 2. But allows for faster data access in blocks. F. FLASH

6. The contents of this memory will persist when the power is removed, but only UV can erase them. D. EPROM (ERASABLE PROGRAMMABLE MEMORY)

explain the need for tall towers on a suspension bridge to ensure stable equilibrium. numeradde

Answers

Tall towers on a suspension bridge are crucial for ensuring stable equilibrium due to the inherent design and structural mechanics of such bridges.

Why are tall towers needed for equilibrium ?

Suspension bridges, renowned for their distinctive features, showcase a suspended roadway and main cables that shoulder the weight and load-bearing responsibilities. The towering structures, also referred to as pylons or piers, rise skyward to fulfill their indispensable role as vertical supports for the primary cables.

The fundamental need for towering structures is rooted in the imperative requirement for ample vertical clearance between the suspended roadway and the surface beneath, be it water or land.

Find out more on suspension bridges at https://brainly.com/question/13199685

#SPJ4

Hello, What type of Pneumatic system that is needed for a Juice
Bottling Plant? can you give examples and explain? thank you!

Answers

Juice bottling plants use a pneumatic system to transfer, fill, and package juice bottles in a more efficient and precise manner. A pneumatic system uses compressed air or gas to transfer, move, or power machinery or equipment.

The types of pneumatic systems that are typically used in a juice bottling plant are air compressors, pneumatic cylinders, valves, and vacuum pumps.There are many different types of pneumatic systems that could be used in a juice bottling plant. For example, a pneumatic cylinder might be used to control the movement of a filling nozzle during the juice filling process. A vacuum pump could be used to transfer juice from one container to another or to fill bottles with juice. Valves are used to control the flow of compressed air or gas in a pneumatic system, and they can be used to turn pneumatic components on and off.In conclusion, a pneumatic system is used in a juice bottling plant to transfer, fill, and package juice bottles efficiently and precisely. Air compressors, pneumatic cylinders, valves, and vacuum pumps are the types of pneumatic systems that are typically used in a juice bottling plant. These pneumatic systems work together to ensure that the juice bottling process is efficient, consistent, and accurate.

To know more about pneumatic system visit :

https://brainly.com/question/29680941

#SPJ11

help protect the lower legs and feet from heat hazards like molten metal and welding sparks

Answers

Answer:

i think its called leggings thats wut my shop teacher told me

Explanation:

Leggings protect the lower legs and feet from heat hazards such as molten metal or welding sparks.

The solute hcl is diffusing through a thin film of water 2 mm thick at 283k. The conc. Of hcl at point 1 is 12wt%hcl (density is 1060kg/m3) and at point 2 is 6 wt%( density= 1030). The diffusivity is 2.45*10^-9 m2/sec.Calculate flux of hcl.

Answers

2.372 x 10 = 23.72 kgmol/sm

what are the SURVEYING INSTRUMENTS​

Answers

Answer:

the main surveying instruments is use around the world are the theodolite, measuring tape, total station, 3D scanners ,GPS/GNSS, level and rod.

Most instruments screw into a tripod when in use.

to avoid falling objects in construction don't stack materials higher than

Answers

Answer:Falling or flying objects on a worksite can expose workers to relatively minor injuries, such as cuts and abrasions, as well as more serious injuries, such as concussions or blindness. Working beneath scaffolds or other areas where overhead work is being performed puts workers at risk from falling objects. Flying objects become a concern when workers are using power tools or performing tasks that involve pushing, pulling or prying.

Explanation:General

Always wear hard hats when work is being performed overhead or when other work conditions call for it.

Stack materials securely to prevent them from sliding, falling or collapsing.

Overhead work

Secure all tools and materials to prevent them from falling on people below.

Use toe boards or guardrails on scaffolds to prevent objects from falling. Alternately, use debris nets or catch platforms to grab falling objects.

Machine use

When working with machines or power tools that can produce flying particles, wear safety glasses, goggles or face shields.

Inspect tools prior to use, and be sure all guards are in place and in good working condition.

Allow only properly trained workers to use power-actuated tools.

Cranes/hoists

Whenever possible, avoid working under moving loads.

Erect barricades and post warning signs at hazardous work zones.

Inspect cranes and hoists prior to use to ensure all components are in good working order, including wire rope, lifting hooks and chains.

Never exceed the lifting capacity of cranes and hoists.

Compressed air

Reduce compressed air for cleaning to 30 psi, and always use proper personal protective equipment and guarding.

Never clean clothing with compressed air.

What is the meaning of beauty and completeness? In relation to these what are the attributes a Muslim should adopt?

Answers

ᴄᴏᴍᴘʟᴇᴛᴇɴᴇꜱꜱ ᴍᴇᴀɴꜱ ᴛʜᴇ ꜱᴛᴀᴛᴇ ᴏꜰ ʙᴇɪɴɢ ᴄᴏᴍᴘʟᴇᴛᴇ ᴀɴᴅ ᴇɴᴛɪʀᴇ; ʜᴀᴠɪɴɢ ᴇᴠᴇʀʏᴛʜɪɴɢ ᴛʜᴀᴛ ɪꜱ ɴᴇᴇᴅᴇᴅ.

ʙᴇᴀᴜᴛʏ ᴍᴇᴀɴꜱ combination of qualities, such as shape, colour, or form, that pleases the aesthetic senses, especially the sight.

Turning operations that require heavy material removal typically use what setting on the
engine lathe?

Answers

Engine latte a mussi coffee chro man ok enign

A small single-cylinder, two-stroke cycle SI engine operates at 4000 rpm with a
compression ratio of 9. At this speed, the engine produces 5 kW of brake power. If
the engine is square with a total displacement volume of 150 cm3
, calculate:
1- Cylinder bore and piston stroke (mm).
2- Crank offset (mm).
3- Average piston speed (m/s).
4- Clearance volume (cm3
).
5- Brake output per total displacement (kW/liter).
6- Number of cycles performed in one second
7- Speed of rotation of the camshaft (rpm)

Answers

I just want the points sry

The demand schedules for Jones, Smith, and other buyers are shown in the table below:
Draw the 4 demand curves for i) Jones ii) Smith iii) Other buyers and iv) All buyers.

Answers

The demand curve is the graphical representation of the relationship between the price of a good and the quantity demanded for a given period of time.

What is a demand schedule?

A demand schedule is a table which shows the quantity demanded of a good or service at different price levels.

A demand schedule can be graphed as a continuous demand curve on a chart where the Y-axis represents the price and the X-axis represents quantity.

Here, a typical representation, the price will appear on the left vertical axis, the quantity demanded on the horizontal axis.

Note that the complete information wasn't found and an overview was given.

Learn more about demand on:

https://brainly.com/question/1245771

#SPJ1

The demand schedules for Jones, Smith, and other buyers are shown in the table below:Draw the 4 demand

We need to support a cylindrical core with a diameter of 8 c m and a length of 22 c m inside a rectangular cavity with dimensions 20 x 20 x 40 c m. Assuming the molten metal has a density of 2. 2 g / c m 3 and the sand core density is 0. 9 g / c m 3 , if each chaplet can support 0. 5 N of force, determine the number of chaplets on top and bottom

Answers

Answer:

####################################

Explanation:

##########################################
###########################
####################################
####################

###############################################
###############################

###########

####################################

##########################

##################################################

Assuming that the quantities of solid wastes generated daily at a commercial facility are distributed normally, with a mean value of 10 yd3 and a standard deviation of 7 yd3, what size container would you recommend for this facility? What are the important tradeoffs in the selection of container size?

Answers

Answer:

The distributions of solid wastes produced daily at a commercial facility are normally distributed with a mean of 10 yd3 and a standard deviation of 7 yd3. If you were to make a container size recommendation for this facility, what size would you propose? What important tradeoffs should be considered when selecting the size of the container?

It's quite perplexing to determine the perfect size of container for a facility whose waste quantity varies and is subject to changes frequently. A certain degree of burstiness is present in the distribution of solid waste generated on a daily basis in a commercial facility. However, using the available mean and standard deviation values, we can infer that a container size of 24 yd3 should be sufficient to hold the daily waste generated, considering that it's two standard deviations above the mean.

When selecting a container size, various tradeoffs must be considered. A large container is more efficient, as it would not require to be emptied as frequently, but it might be expensive and may take up more space. A smaller container may be less expensive and take up less space, but it would need to be emptied more frequently, which can result in higher transportation costs and more time spent on waste management. It is therefore essential to strike a balance between the frequency of emptying and the container size to ensure that the waste is managed effectively and efficiently.

To determine the appropriate container size, we need to consider the mean value and the standard deviation of the daily solid wastes generated at the commercial facility. Since the data is normally distributed, we can use the following formula to calculate the container size:

Container size = mean + z-score * standard deviation

To determine the appropriate z-score, we need to refer to a standard normal distribution table. Assuming a 95% confidence interval, the z-score would be 1.96. Therefore, the container size would be:

Container size = 10 + 1.96 * 7
Container size = 23.32 yd3

Based on this calculation, we would recommend a container size of 24 yd3 to ensure that it can accommodate the average daily waste generated at the facility.

When selecting a container size, there are several important tradeoffs to consider. A larger container size may be more expensive to purchase and maintain, but it can help reduce the frequency of waste removal and transportation, which can save costs in the long run. On the other hand, a smaller container size may be more affordable, but it may require more frequent waste removal, which can increase transportation costs and result in more greenhouse gas emissions. Additionally, the facility's available storage space and access to waste removal services should also be considered when selecting an appropriate container size.

A linear frequency-modulated signal makes a good test for aliasing, because the frequency moves over a range. This signal is

Answers

The signal called “chirp”
Other Questions
What is the distance of an object that has an angular diameter of 10 arc-seconds and a distance of 50,000 meters the term used to describe the benefits produced by a merger or acquisition is _____. Which of the following stimuli would cause the liver to produce more glycogen?Question options:A) Going several hours without eating anythingB) Consuming a breakfast sandwich containing many carbohydratesC) Going several hours without drinking anythingD) Consuming a steak containing many proteins What does mean in wavelength? Kwan's beginning account balance was $20. His ending balance is $0. What integer represents the change in his account balance from beginning to end? if the odds are 8 to 1 against a team winning (they lose more than they win), what is the probability the team wins? A programmer must write a program that lists all the words that appear in a text file that occur more than 10 times. Which of the following tasks would be a good first step in an incremental programming process? a Display a list of all the unique words in the file. b Display the file's contents. c Display a table of all the words in the file, with how many time that word occurs. d Write any import statements needed for the program, and print "Done Step 1". Q3) How many years would it take an investment of $314.00 to grow to $48,236.00 at an annual rate of return of 15.96% ? (1.5 points) Simplify. -[tex] \sqrt{ {m}^{4} {n}^{7} [/tex]please simplify Chamberlain Co. wants to issue new 13-year bonds for some much-needed expansion projects. The company currently has 10.0 percent coupon bonds on the market that sell for $1,059.95, make semiannual pay Given the quadratic equation f(x)=3x2+8x+8 what is the y-coordinate of the vertex? (round-off to 3 decimal places) Your Answer: Answer 2. If the employees in this organization (specifically your selected job) unionized, in what ways would the HR decisions that you made in Parts? to 3 of this project possibly change or be impacted? 3. In what ways would the HR decisions that you made in Parts 2 and 3 of this project be different if you were sending this employee to a different country to perform this job? How where big land owners lifes before the revolutionary war Write a linear equation with a slope of 14 and y-intercept -12. 5. A person's weight varies directly with gravity. If a person weighs 180 pounds on Earth, they will weighonly 30 pounds on the moon. If Haresh weighs 54 pounds on Earth, how much would he weigh on themoon? You must evaluate a proposal to buy a new milling machine. The purchase price of the mulling machine, including shipping and installation coses, is $139,000, and the equpment wall be fully depreciated at the time of purchase. The machine would be sold after 3 years for $82,000. The machine would require a $3,500 increase in net operating workang capital (increased inventory less increased accounts payable). There woild be no effect on revenues, but pretax labor costs would decline by $51,000 per year. The marginal tax rate is 25%, and the WACC is 12%. Aso, the firm spent $4,500 last year investigating the feosibility of using the machine. a. How should the 54,500 spent last year be handed? 1. Last year's expenditure is considered a sunk cost and does not represent an incremental cash flow, Hence, it should not be included in the analysis. 11. The cost of research is an incremental cash flow and should be included in the analysis. III. Only the tax effect of the research expenses should be included in the analysis. IV. Last year's expenditure should be treated as a terminal cash flow and dealt with at the end of the project's lefe. Hence, it should not be induded in the inital investment outlay. V. Last year's expenditure is considered an opportunity cost and does not represent an incremental cashiflow. Hence, it should not be induded in the analysis. Jonathon collected 4 1/2 kg of seashells. If he gives 2 3/4 kg of seashells to his friend, what is the weight of theremaining seashells that Jonathon has? Write two adjectives or descriptive phrases that describe the term, person, or event. 1. charter A NO PASSING ZONE road sign has the shape of anisosceles triangle with angle measures shown. Writeand solve an equation to determine the value of x.Round to the nearest tenth.(3.25x)"NOPASSINGZONE*50*X= Was the internment of Japanese Americans on the west coast during the war justified?