Develop a Work Breakdown Structure for the following scenario:
A retail chain in California is planning to implement a new ERP system – Finance and HR modules. They have hired 2 ERP consultants from a Big 8 consulting firm.
Consultants identified the following major tasks: Gap Analysis, Customize for company specific functions, Testing existing and customized functions and final overall system testing, Deployment Planning, Execution, and final production.
Develop a WBS (Work Breakdown Structure) to be used for detailed tasks scheduling.

Answers

Answer 1

Work Breakdown Structure (WBS) for Implementing a New ERP System - Finance and HR Modules:

1. Project

and Preparation

  1.1 Define project objectives and scope

  1.2 Identify project team and roles

  1.3 Set project milestones and deliverables

  1.4 Develop project timeline and schedule

  1.5 Allocate resources and budget

2. Gap Analysis

  2.1 Conduct initial assessment of current systems and processes

  2.2 Identify gaps between current state and desired future state

  2.3 Document requirements for system customization and configuration

Note: The WBS provided is a high-level breakdown of the tasks involved in implementing a new ERP system - Finance and HR modules. It can be further detailed by breaking down each task into subtasks and assigning resources, dependencies, and timelines.

Learn more about budget here:

https://brainly.com/question/31952035

#SPJ11


Related Questions

Miguel is vice president of marketing at xyz corp. He is disappointed to learn that the vice president of sales at xyz earns 20 percent more than he does despite the two positions having similar levels of responsibility and impact. In this example, what method is miguel using to evaluate the fairness of his pay?

Answers

Miguel holds the position of vice-president of marketing at xyz Corp. Because Miguel ended up having $35 more so than he did, he is unsatisfied.

What are the many types of marketing?

The 4 P are a "combination of strategies" that includes four crucial elements for selling a product or service product, price, place, and marketing. Businesses frequently consider the four Ps when creating plans and objectives for reach their intended audiences.

What is an effective marketing example?

In a word, it is an effort to make customers aware of a business's offers, which can include both physical goods for sale or services rendered. Advertising on television, on billboards along the highway, and in magazines are all common examples of marketing in action.

Briefing

He spends $35 × 4 = $140.

He earns $21 × 5 = $105.

His net increase is $105 -140 = -$35.

Miguel ends up with $35 less than he started with.

To know more about marketing  visit:

https://brainly.com/question/11531316

#SPJ4

Mary remodeled her bathroom, and her assessment went from $67,000 to $71,000. If she pays taxes at a rate of 31.5 mills, what is her increase in property tax?

Answers

Answer:

$126

Explanation:

To solve, find the amount of property tax at $67,000, then find the amount of property tax at $71,000 and subtract the amounts.

Mary remodeled her bathroom, and her assessment went from $67,000 to $71,000. If she pays taxes at a rate of 31.5 mills, Then her increase in property tax will be $126.

What is tax?

The taxes are mandatory contributions, that are levied on individuals or corporations by a government entity—whether local, regional, or national.

The tax revenues are basically used for financing government activities, including public works and services such as construction of roads, hospitals and schools, or programs such as Social Security, old age pension and Medicare.

In economics, taxes fall on whoever pays the burden of the tax, whether this is the entity being taxed, such as a business, or the end consumers of the business’s goods.

Mary remodeled her bathroom, and her assessment went from $67,000 to $71,000. If she pays taxes at a rate of 31.5 mills, Then her increase in property tax will be $126.

Learn more about tax here:

https://brainly.com/question/16423331

#SPJ6

cross-docking: multiple choice sorts items for production support. stores inventory to support seasonal demand. combines break-bulk and consolidation activities. supports reverse logistics.

Answers

Cross-docking: selecting items for production support using a variety of criteria.

Option -combines break-bulk and consolidation activities

Cross-docking is a logistics technique where items are sent straight from a manufacturer or mode of transportation to the customer or another mode of transportation with little to no storage in between. This can be done in order to switch the mode of transportation, sort the material into different destinations, or put materials from various origins into transport vehicle (or containers) that are headed in the same or comparable directions.

In a distribution docking terminal, which typically has trucks and dock doors on two sides (inbound and outgoing) with little storage space, cross-docking occurs.

Cross-docking is the process of transporting cargo from one transport vehicle directly onto another in the LTL trucking industry, with little to no warehousing. Staging zones may be used for cross-docking operations in retail.

Learn more about Cross-docking here:

https://brainly.com/question/13896081

#SPJ4

A 3rd degree burn has burnt only part of the epidermis. the epidermis only. the epidermis and dermis. the epidermis and part of the dermis.

Answers

A 3rd degree burn has burnt the epidermis and part of the dermis. Option 3 is the correct answer.

A 3rd degree burn is a severe burn that extends through the entire thickness of the skin. In a 3rd degree burn, the epidermis, which is the outermost layer of the skin, and part of the dermis, which is the layer beneath the epidermis, are affected. This type of burn destroys the full thickness of the epidermis and can extend into the deeper layers of the dermis.

The epidermis serves as a protective barrier for the body, preventing the entry of harmful substances and pathogens. It also helps regulate body temperature and plays a role in the production of vitamin D. The dermis provides structural support, contains blood vessels, nerve endings, sweat glands, and hair follicles.

Due to the severity of the injury, 3rd degree burns often require medical intervention and specialized treatment. They can result in extensive tissue damage, loss of sensation, and impaired healing. Treatment may involve surgical interventions, such as skin grafting, to promote healing and minimize the risk of infection. Rehabilitation and long-term care are often necessary to manage the physical and psychological effects of a 3rd degree burn.

Hence, option 3 is the right choice.

To know more about epidermis , visit https://brainly.com/question/13450121

#SPJ11

a company issues $500,000 of 6%, 10-year bonds dated january 1, 2017 that mature on december 31, 2026. the bonds pay interest semiannually on june 30 and december 31 each year. if bonds are sold at par value, the issuer records the sale with which of the following entries? multiple choice question. debit to cash $500,000; and credit to bond payable $500,000. debit to bond payable $500,000; and credit to cash $500,000. debit to cash $500,000; debit to interest expense $300,000; and credit to bond payable $800,000.

Answers

A company issues $500,000 of 6%, 10-year bonds dated January 1, 2017 that mature on December 31, 2026. If bonds are sold the entries are:  Debit to Cash $500,000; and credit to Bond Payable $500,000.

Option A is correct.

Bond payable:

Bond payable are form of debt securities are a type of debt financing issued by corporations, governments, and other entities to raise capital. As part of the financing, the issuer of the bond is obligated to make periodic interest payments over the term of the loan and to repay the principal when due.

Where will the bond be paid?

As the bond issuer, the company is the borrower. Therefore, issuing a bond creates a liability. Liabilities therefore appear on the liability side of the company's balance sheet. Fixed Income liabilities are generally classified in the long-term liability class.

Learn more about Bond payable:

brainly.com/question/28093147

#SPJ1

the following graph displays four supply curves (ll, mm, nn, and oo) that intersect at point v. 0 2 4 6 8 10 12 14 16 18 20 20 18 16 14 12 10 8 6 4 2 0 price (dollars per unit) quantity (units) v w x y z m m o o l l n n using the graph, complete the table that follows by indicating whether each statement is true or false. statement true false between points v and w, curve nn is perfectly inelastic. curve ll is more elastic between points v and x than curve oo is between points v and y. between points v and y, curve oo is inelastic.

Answers

The table indicating whether each statement is true or false based on the given graph areStatementTrueFalseBetween points v and w, curve nn is perfectly inelastic. Between points v and x, curve ll is more elastic than curve oo is.√Between points v and y, curve oo is inelastic. Perfectly inelastic supply curve is represented by a vertical line on the graph. In this graph, the supply curve nn is a vertical line.

The vertical line represents that any change in the price of the product would have no effect on the supply of the product, hence true. For elastic supply curves, a small change in the price results in a large change in the quantity supplied. Curve ll has a steeper slope than curve oo between points v and x, so curve ll is more elastic than curve oo, thus true.

Inelastic supply curves are those in which a change in price has little effect on the quantity supplied. Curve oo has a less steep slope between points v and y, so curve oo is inelastic, thus true.curve nn is perfectly inelastic.√Between points v and x, curve ll is more elastic than curve oo is.√Between points v and y, curve oo is inelastic.√Perfectly inelastic supply curve is represented by a vertical line on the graph. In this graph, the supply curve nn is a vertical line.

To know more about graph Visit:

https://brainly.com/question/17267403

#SPJ11

In terms of SUPPLY, what factors have contributed to the fall in oil prices?

Answers

Current supply and output. Until recent years, Organization of Petroleum Exporting Countries (OPEC) often set supply through a quota system.

Assume Chobot First National Bank is fully loaned up and that the reserve requirement is 20%. Mikey deposits $1,000 into the bank.

(A)Calculate the impact of this deposit on the M1 measure of the money supply. (Calculate means show your work.)
(B)Explain two limitations of the money creation process.
(C)Suppose the reserve requirement is lowered to 10% instead of 20%. Explain how the reduction in the reserve requirement affects the total money supply and how much money the bank can create using the new reserve requirement, if Mikey deposits $1,000 into the bank.

Answers

The impact of Mikey's deposit on M1 measure of the money supply is an increase of $5,000.

What is money supply?

Money supply refers to the total amount of money that is circulating within an economy at a given time. It includes all forms of money such as physical currency, bank deposits, and other types of liquid assets that can be easily converted into cash. The central bank of a country, such as the Federal Reserve in the United States, has the authority to regulate the money supply by controlling the amount of money that banks can lend or by buying or selling government securities. The level of money supply in an economy can have a significant impact on inflation rates, interest rates, and economic growth. Understanding the money supply is important for policymakers, economists, and investors alike as it can affect investment decisions and economic stability.

Mikey's $1,000 deposit increases bank's reserves by $1,000 * 20% = $200, leaving $800 in excess reserves.

Therefore, total increase in money supply is $1,000 (Mikey's deposit) + $4,000 (new loans created) = $5,000.

To learn more about money supply, visit:

https://brainly.com/question/30218160

#SPJ1

Autocratic managers tend not to _____.

Answers

Answer:

Autocratic managers don't entertain any suggestions or consider initiatives from subordinates. This style of management is effective for quick decision making but is generally not successful in fostering employee engagement or maintaining worker satisfaction.

Explanation:

Why are tradeoffs necessary?
a. Resources are limited
b. People want different things
C. Every product has flaws
d. Advertisers promote products

Answers

Answer:

trade offs are necessary because resources are limited,people want different things, every product has flaws, and advertisers can promote products.

[Preferred Stock Characteristics] A share of a venture’s preferred stock is convertible into 1.5 shares of its common stock. The dividend on the preferred stock is $0.50 per share.

A. If the firm’s common stock is currently trading at $9.75, what is the conversion value of a share of the preferred stock?

B. What would be the dividend yield on the preferred stock based on its conversion value?

C. What explanation would you give if the venture’s preferred stock currently trades at $15? What would be the dividend yield?

D. If the venture doubles the number of shares of its common stock that are outstanding (and cuts its stock price in half) but increases the conversion terms on its preferred stock to 2.5 shares of common stock, what would be the conversion value of a share of preferred stock after the new common stock issue? What would be the dividend yield on the preferred stock based on this new conversion value?

E. If the venture increased its common stock offering by 50 percent (instead of 100 percent), what common stock conversion ratio would be needed on a share of preferred stock to keep its conversion value the same as it was before the new common stock issue?

Answers

The conversion value of a share of the preferred stock is $14.63. The dividend yield on the preferred stock, based on its conversion value, is 3.41%. The dividend yield on the preferred stock, based on the $15 trading price, is 3.33%. The dividend yield on the preferred stock, based on the new conversion value, is 4.10%.

Conversion value = Conversion ratio × Common stock price

Conversion value = 1.5 × $9.75 = $14.63

Dividend yield = Dividend per share / Conversion value

Dividend yield = $0.50 / $14.63 = 0.0341 or 3.41%

Dividend yield = Dividend per share / Preferred stock price

Dividend yield = $0.50 / $15 = 0.0333 or 3.33%

Conversion value = Conversion ratio × Common stock price

Conversion value = 2.5 × ($9.75 / 2) = $12.19

Dividend yield = Dividend per share / Conversion value

Dividend yield = $0.50 / $12.19 = 0.0410 or 4.10%

Common stock conversion ratio = Original conversion value / (Common stock price × 1.5)

Common stock conversion ratio = $14.63 / ($9.75 × 1.5) = 1

The dividend yield is a financial metric that indicates the annual return on investment in the form of dividends distributed by a company. It is calculated by dividing the annual dividend payment per share by the stock's current market price per share and expressing the result as a percentage.

A high dividend yield suggests that a company is distributing a larger portion of its profits to shareholders as dividends, making it an attractive investment option for income-seeking investors. Conversely, a low dividend yield may indicate that a company is retaining more of its profits for reinvestment or other purposes. Investors often use dividend yield as one of the factors to assess the attractiveness of a stock.

To know more about Dividend yield refer to-

brainly.com/question/27878436

#SPJ4

An architect’s functions may include which of the following? (SELECT ALL THAT APPLY.)

-planning and designing houses, commercial buildings, and other structures
-ensuring worksite safety
-collaborating with engineers
-acting as a construction manager and supervising contractors

Answers

The answer is a b and d

Answer:

the answer is planning, ensuring, and acting

Which are examples of copyrighted online materials? Check all that apply.

an article from an Internet magazine
lyrics for a song written in the 1800s
photos taken by a student on his blog
a video game that is free for anyone to copy
an illustration sold by an artist on her website
an excerpt from a novel published in 1913

Answers

Answer:

a and d

Explanation:

Answer:

A & E

Explanation:

edge test

Excuse me,



(ಠ_ಠ)
ง ง

Answers

Answer: >:o
Explanation:

Many corporations are shifting from defined benefit to defined contribution retirement programs. When considering changes to retirement programs, the primary stakeholders are the.... a. shareholders b. competition c. employees e. marketing managers. f. customers

Answers

C) Many businesses are converting their retirement plans from defined benefits to defined contributions. The employees are the main stakeholders when modifying retirement programs.

Stakeholders are what?

Stakeholders are organizations that have an interest in a project or commercial venture's success. Stakeholders have a vested interest in the project's success, whether they are a part of the supporting organization or not. The success of every project depends on stakeholders because of their ability to make decisions.

Without the backing of significant or crucial stakeholders, a project cannot succeed. A stakeholder is a person, just like any other project participant, but some are easier to manage than others. To identify your key stakeholders and make sure you are serving their needs, you'll need to gain the ability to utilize stakeholder mapping methodologies.

Learn more about stakeholders with the help of the given link:

brainly.com/question/29532080

#SPJ1

The economic term used to describe the federal reserve's actions to determine the size of the supply of money in the nation and the level of interest rates is

Answers

Monetary policy generally can be described as the federal reserve's actions to determine the size of the supply of money in the nation. Monetary police activities is taken by central bank, such as the Federal Reserve.

Monetary policy generally can be described as the macroeconomic policy laid down by the central bank. Monetary policy involves interest rate and  management of money supply and also is the demand side economic policy used by the government of a country to achieve macroeconomic objectives like growth, inflation, consumption,  and liquidity.

Here you can learn more about monetary policy in the link https://brainly.com/question/30040431

#SPJ4

Accountants argue that it may not be appropriate to evaluate managers of subsidiaries based solely on indicators of profitability because they do not operate in a uniform environment.T/F

Answers

True - Accountants argue that it may not be appropriate to evaluate managers of subsidiaries based solely on indicators of profitability because they do not operate in a uniform environment.

assessment is a scientific determination and assessment of a subject's advantage, well worth and significance, the usage of standards ruled by using a set of standards. it is able to help an corporation, program, layout, task or any other intervention or initiative to assess any goal, realisable idea/inspiration, or any alternative, to assist in choice-making; or to check the diploma of fulfillment or value in regard to the goal and targets and consequences of such a action that has been finished.[1] The number one reason of assessment, in addition to gaining insight into previous or current projects, is to allow mirrored image and help in the identification of destiny alternate.

Learn more about evaluate here

https://brainly.com/question/25907410

#SPJ4

Many politicians have degrees in business or law.

True
False

Answers

the answer is trueee

enny starts a business and 4.2%/ a compounded monthly. She can afford to make payments between $1000 and $1500 per month. How much sooner can she pay off the loan if he pays the maximum amount compared with the minimum amount?

Answers

Jenny's business loan is growing at a compounded monthly rate of 4.2%. To pay it off sooner, she can make payments between $1000 and $1500 per month. Assuming the initial loan amount is $100,000, let's calculate the payment needed to pay it off in 10 years (120 months) with the minimum amount of $1000 per month using the formula:

\(P = (r/n) * A / [1 - (1 + r/n)^(-nt)]\) where P is the monthly payment, r is the monthly interest rate (4.2% divided by 12), n is the number of compound periods per year (12), A is the initial loan amount, and t is the length of the loan in years (10). We get P\(= ($100,000 * 0.042 / 12) / [1 - (1 + 0.042 / 12)^(-12*10)] = $1,044.\)  Now, let's calculate the payment needed to pay off the same loan amount in 10 years (120 months) with the maximum amount of $1500 per month: P \(= (100,000 * 0.042 / 12) / [1 - (1 + 0.042 / 12)^(-nt)]\)  = $1500 Solving for t, we get t \(= -log(1 - ($1500 * (0.042/12) / $100,000)) / log(1 + (0.042/12)) = 7.3\)years or 88 months.

Therefore, if Jenny pays the maximum amount of $1500 per month versus the minimum amount of $1000 per month, she can pay off the loan 32 months (120 - 88) sooner.

Question is incomplete the complete question is

Jenny starts a business and 4.2%/ a compounded monthly. She can afford to make payments between $1000 and $1500 per month. How much sooner can she pay off the loan if he pays the maximum amount compared with the minimum amount?

To know more about business loan visit:

https://brainly.com/question/14093526

#SPJ4

. You use the utility company’s budget plan for paying your home heating bills. You pay $75 per month for 9 months. Your actual bills are: $28.95, $46.15, $68.46, $109.34, $115.26, $94.19, $75.66, $51.97, $49.16. Compute the average for 9 months.

Answers

Answer:

$71.01

Explanation:

An average is a number expressing the central or typical value in a set of data, in particular the mode, median, or (most commonly) the mean, which is calculated by dividing the sum of the values in the set by their number.

Given

September, $28.95;

October, $46.15;

November, $68.46;

December, $109.34;

January, $115.26;

February, $94.19;

March $75.66;

April, $51.97; and

May, $49.16.

Step two:

Total amount= 28.95+46.15+68.46+109.34+115.26+94.19+75.66+51.97+49.16= 639.14

Total number of monts= 9

Average= 639.14/9

Average= $71.01

In which quadrant or quadrants of the strategic grid, throughout the timeline of the case, would
you place Bharti Airtel’s Information Technology? Motivate your answer

Answers

The factory, strategic, support, and turnaround quadrants make up the strategic impact grid. The IT Strategic Grid is a structure comprised of four quadrants, each of which refers to one of four possible functions for information systems and IT inside an organisation.

One of the four divisions on a Cartesian plane is a graph quadrant. There is a certain set of negative and positive values for x and y in each of the four sections. An ordered pair is plotted on graph quadrants. Ordered pairs have values for x and y. In an ordered pair, X is the first value and y is the second. The strategic grid enables analysis of the placement of the IT department within the organisational structure and of IT management.

To learn more about Strategic, click here.

https://brainly.com/question/26960576

#SPJ4

The advertising industry was worth how much money in 1920?

$3,000

$300,0000

$3,000,000,000

$300,000,000

Answers

Answer:

3,000,000,000

Explanation:

let me now if I'm wrong

based on the information you were provided, which of the options is the most accurate statement with respect to the possible transition of the software qa function to baltonia? select an option from the choices below and click submit. staying in genovia is riskier, because staying with a process is always riskier in a dynamic business environment. moving to baltonia involves greater risks but also potentially greater rewards. moving to baltonia involves greater risks and no benefits to balance those risks.

Answers

With regard to the prospective transition of software qa functions to Baltonia, the truest statement based on the facts presented to you is that migrating from alternatives to Baltonia has a higher risk but could also result in better rewards. Here option B is correct.

In any organizational change, there are always risks and rewards involved. Moving the software QA function to Baltonia may offer some potential benefits, such as access to a new pool of talented professionals, lower costs, and a new market to expand the business. However, it also involves risks such as cultural differences, regulatory compliance issues, communication barriers, and potential disruptions to the existing workflow.

On the other hand, staying in Genovia may provide some level of stability and familiarity. However, the risk of becoming complacent and outdated in a dynamic business environment can be high. Additionally, staying in the same location may limit the potential for growth and expansion.

Therefore, the most accurate statement depends on the specific circumstances and considerations involved in the decision. In general, it is important to carefully assess the risks and benefits of any organizational change and make an informed decision based on a thorough analysis of the available information.

To learn more about organizational change

https://brainly.com/question/29764667

#SPJ4

Complete question:

Based on the information you were provided, which of the options is the most accurate statement with respect to the possible transition of the software qa function to Baltonia? select an option from the choices below and click submit.

A - staying in Genovia is riskier because staying with a process is always riskier in a dynamic business environment.

B - moving to Baltonia involves greater risks but also potentially greater rewards.

C - moving to Baltonia involves greater risks and no benefits to balance those risks.

mallory is looking for a part-time job at a coffee shop. she looks in the classified section of a local newspaper and finds an ad for a part-time barista. the ad states that the person filling this position will be responsible for brewing coffee and preparing specialty coffee drinks. this classified ad in the newspaper provides mallory with the __

Answers

The classified ad in the newspaper provides Mallory with the job opportunity for a part-time barista position at a coffee shop.

A classified ad in a newspaper is a common method for employers to advertise job openings. In this case, Mallory has come across a classified ad for a part-time barista position at a coffee shop, which is a job opportunity for her.

A barista is a skilled coffee maker who prepares and serves specialty coffee drinks, such as lattes, cappuccinos, and espresso shots.

Baristas may also be responsible for greeting customers, taking orders, handling cash and credit card transactions, and keeping the coffee shop clean and well-stocked.

A part-time position typically involves working fewer hours than a full-time position, and may be ideal for students, people with other part-time jobs, or those looking for a more flexible work schedule.

Part-time positions may also offer fewer benefits than full-time positions, such as health insurance or paid time off.

To learn more about opportunity, refer below:

https://brainly.com/question/29341508

#SPJ11

Let the principal be 4,000JPY and the annual interest rate 10%, in compound interest. Then, 3 year later, the included amount is (a) UPY).

Answers

After 3 years, the included amount is approximately 5,324 JPY.

To calculate the amount after 3 years using compound interest, we can use the formula:

A = P * (1 + r/n)^(n*t)

Where:

A = the final amount

P = the principal amount

r = the annual interest rate (in decimal form)

n = the number of times interest is compounded per year

t = the number of years

In this case, the principal (P) is 4,000 JPY, the annual interest rate (r) is 10% (0.10 in decimal form), and we want to find the amount after 3 years.

Let's assume that interest is compounded annually (n = 1).

A = 4,000 * (1 + 0.10/1)^(1*3)

A = 4,000 * (1 + 0.10)^3

A = 4,000 * (1.10)^3

A = 4,000 * 1.331

A ≈ 5,324.00 JPY

Therefore, after 3 years, the included amount is approximately 5,324 JPY.

To know more about compound interest, visit:

https://brainly.com/question/14295570

#SPj11

For the fall semester, you had to pay a nonrefundable fee of $600 for your meal plan, which gives you up to 150 meals. If you eat 100 meals, your marginal cost of the 100th meal is: Group of answer choices

Answers

Answer:

$6

Explanation:

Marginal cost is additional cost for producing one extra unit of product

The given parameters are;

The amount paid for the semester meal plan = Nonrefundable $600

The number of meals that can be eaten with the meal plan = 150

The number of meals ate = 100

Therefore, at $600, the marginal cost of the 100th meal is the cost of producing 100 meals at $600 given as follows;

Marginal cost of a meal = Total amount paid for the semester meal plan/(Total number of meals taken)

The marginal cost of the 100th meal = $600/100 = $6.00

The marginal cost of the 100th meal  = $6.00

The marginal cost of the 100th meal is $6.

Calculation of the marginal cost:

Marginal cost refers to the additional cost for generating one extra unit of product

Since

The amount paid for the semester meal plan = Nonrefundable =  $600

The number of meals that can be eaten with the meal plan = 150

The number of meals ate = 100

Now

Marginal cost of a meal = Total amount paid for the semester meal plan/(Total number of meals taken)

= $600/100

= $6.00

Hence, The marginal cost of the 100th meal  = $6.00

learn more about marginal cost here: https://brainly.com/question/10742640

Why does an enterprise need to listen to its customers

Answers

so they will get more customers
In order to keep the customers they currently have satisfied as well as gain new ones. The more customers they have, the more money they will make and that is the end goal.

define ecommerce in business with example​

Answers

Answer:

See below

Explanation:

eCommerce refers to business transactions conducted via internment. eCommerce is the short form of electronic commerce. It is the selling and buying of products and services through the internet platform. eCommerce includes other commercial transactions conducted online such as online/internet banking, online money transfers, online auctions, ticketing, and payments.

An example of eCommerce is the online retail stores where shoppers pick and select merchandise on the retail store's website and pay online. The retail store then organizes for the items to be delivered to the customer's premises.

Why is the Federal Reserve so important? What services do they offer?

Answers

The Federal Reserve is important because it is the central bank of the United States and is responsible for managing the nation's monetary policy.

The Federal Reserve's policies can affect interest rates, inflation, employment, and economic growth. The Fed also serves as a lender of last resort during times of financial crisis, providing liquidity to banks and other financial institutions to help prevent economic collapse. The Fed also maintains the stability of the financial system by supervising and regulating banks and other financial institutions to ensure their safety and soundness.

Finally, the Federal Reserve plays an important role in promoting financial stability and consumer protection through its oversight of consumer lending and its role as a watchdog for systemic risks in the financial system. Overall, the Federal Reserve plays a crucial role in promoting economic growth, stability, and prosperity in the United States.

To know more about Federal Reserve, click here:

https://brainly.com/question/23247429

#SPJ11

What is considered a human rights abuse by an American company may be viewed as an acceptable business practice in China, which illustrates that ______. Multiple choice question. better ethics comes with increased standard of living the United States is often overly critical of foreign business practices the United States has more highly evolved ethical practice moral standards are relative to particular societies

Answers

What is considered a human rights abuse by an American company may be viewed as an acceptable business practice in China, which illustrates that moral standards are relative to particular societies.

What are moral standards?

In summary, moral standards are what a person of society considers to be right or wrong regarding human behavior. These standards are often different in the distinct cultures and societies around the world, often due to differing histories that helped to form them.

Therefore, we can confirm that the situation described in the question is a direct result of the moral standards being relative to particular societies.

To learn more about societies visit:

https://brainly.com/question/8706433?referrer=searchResults

Other Questions
which of the following states has the greatest protection for freedom of the press based on the information on the map? responses new york (ny) missouri (mo) wyoming (wy) georgia (ga) A comparison and contrast essay should provide _____. what volume (in ml) of 0.500 m hcl would be needed to react with 0.0357 g of al metal? hint: write a balanced reaction first. the molar mass of al is 26.98 g/mol. therapists utilizing motivational interviewing strategies view clients as What important development came out of the battle of Cowpens A pictorial drawing is a three-dimensional drawing that gives the viewer an overall impression of how an object should look which is an accurate statement about italian baroque artist caravaggio's approach to painting? 0 calling of saint matthew, painting by michelangelo merisi da caravaggio, showing light illuminating men sitting around a table looking at christ responses 0 caravaggio focused on depicting narrative historical themes. 0 caravaggio focused on depicting narrative historical themes. 0 caravaggio created dramatic compositions that focus on realism. 0 caravaggio created dramatic compositions that focus on realism.0caravaggio used foreshortening to depict a sense of flattened space. 0 caravaggio used foreshortening to depict a sense of flattened space. 0 caravaggio painted religious scenes with idealized figures. New York City is either in the U.S.A. or France. But it's not in France. It follows that New York City is in France.Is the deductive argument valid or invalid? Find the value of x, y, and z in the rhombus below(-x-8)107(3y-1)(-4z-7) Who was considered to be the spiritual guardian of the family? a. The paternal grandfatherb. The fatherc. The maternal grandmother d. A child who died at birth e. The mother Jim is building a model airplane the scale is 2 inches to 40 inches the actual week wingspan of the plane is 220 feet how long will the wingspan of the model B which of the following sentences has a misplaced modifier? question 42 options: we have compiled a list of selected candidates using the employment criteria posted on our website. rory was asked to create a report on the implications of the new policy. on wednesday, the council decided to apply for a grant. sarah asked aaron to revamp the company website to make it appear more sophisticated. the company charges its customers only after they have received their order. most students believe they are best prepared in the area of critical and analytical thinking when they graduate from college. in which area do employers find students well prepared? group of answer choices A salesperson's weekly paycheck is 40% more than a second salesperson's paycheck. The two paychecks total $1375. Find the amount of each paycheck.nearest cent.)first salesperson's paycheck $ 843.75Xsecond salesperson's paycheck $ 63125X In a laboratory, the number of bacteria in a petri dish after t days is modeled by the function b (t) = startfraction 300,000 over 1 999 e superscript negative 0.5 t baseline endfraction. what does 300,000 represent? initial number of bacteria in the petri dish number of bacteria in the petri dish after one day number of bacteria in the petri dish at any given time maximum number of the bacteria the petri dish can hold what is the measure of abd which of the following are risk factors for cancer? select 3 correct amswers How can i weld an 8-PIN DIN adapter that goes to 2 RCA'S (for audio), here is the diagram of the 8-PIN DIN, I need help!! What made the Zhou Dynasty the longest lasting in Chinese history? The following problem must be solved analytically, without usingmathematical formulas or equations. Express how it is solvedliterally.The component of the magnetic field of a spherical wave in spac