The concept of ‘critical path’ can often be confusing, as many students want to believe that it is the ‘shortest’ path through a network. Convincingly explain why this is not so. Explain how the critical path defines the project’s duration and how "crashing" affects that

Answers

Answer 1

In regards to the specific question about the concept of the critical path, it is important to note that the critical path is not necessarily the shortest path through a network.

What's critical path

The critical path is actually the longest path through a network, and it defines the project's duration. This means that any delays on the critical path will directly impact the project's completion date.

"Crashing" refers to the process of shortening the project's duration by compressing activities on the critical path. This can be achieved by adding additional resources, reducing the scope of work, or using alternative materials.

By crashing the critical path, the project team can potentially reduce the project's duration, but this typically comes at an increased cost.It is important for students to understand the concept of the critical path in order to effectively manage and execute complex projects.

By understanding the critical path and the impact of delays on the project's completion date, project managers can better allocate resources and develop contingency plans to ensure project success.

Learn more about critical path at

https://brainly.com/question/16519233

#SPJ11


Related Questions

The history of bananas
Using at least two terms from the unit, summarize the United States’ connection to the history of bananas, as documented in this TED talk.

The history of bananasUsing at least two terms from the unit, summarize the United States connection

Answers

There was a U.S corporation called El Pupo that specialized in trafficking bananas. Bananas fist officially reached America in the early 1500’s. By the end of the 1800’s, bananas were a big hit in the U.S.

How was bananas shoot introduced to the US for cultivation?

Spanish explorers brought bananas to the Americas in the 1500s. The first banana shoot is thought to have been planted in the Caribbean islands in 1516. Bananas did not arrive in the United States until the 1800s, when sailors brought banana shoots back from the Caribbean.

Because fruit companies in the United States wanted to grow their own bananas, they bribed government officials to gain access to various lands. Rainforests were cleared, plantations were constructed, and the business grew from there.

Read more about bananas

brainly.com/question/10713285

#SPJ1

In what areas do federal agencies regulate to ensure safety and the general
wellness of US citizens?

a. Businesses
b. Environment
c. Products
d. All of the above

Answers

Answer:

d. All of the above

Explanation:

Government regulations are the rules that players in an industry must abide by. In a free-market economy like the US, the government's main role is to regulate economic activities. The government enforces regulation through its various agencies.

The areas of regulations include but are not limited to

Protecting consumers from undue exploitation by businesses, Encourage fair business competition Promote a healthy, safe work environment for employees Promote and sustain a clean environmentPrivate data protection and security

pls help Many four-year colleges require which one of the following exams?

a.AP

b.SAT

c.ASVAB

d.PSAT

Answers

Many four-year colleges require b.SAT exams.

What is SAT exams?

The SAT  can be described as internattional exam that is been carried out which do serves as the  standardized test widely used for college admissions  especially in the United States.

It should be noted that this exam is widely accepted and can be used to covers reading, writing, and math which is been used in the process of accessing the student so that they can moveto higher levels in their academic endeaveors.

Learn more about SAT exams at:

https://brainly.com/question/16844356

#SPJ1

1,Discuss how China’s lockdown created an impact tothe global supply chain network? If you are anautomotive part supplier in Thailand, what are the operations management concepts that should be implemented to handle this situation?
2,As inflation in food prices and cost of living in Thailand, is currently increasing, as a CEO of SMEscompany in Thailand, what action(s) should be taken to generate more revenue and lower operational costs for the company?

Answers

China's lockdown during the pandemic caused significant disruptions to the global supply chain network. As an automotive part supplier in Thailand, implementing operations management concepts like supply chain diversification, demand forecasting, cost optimization, and supplier relationship management is essential to handle the situation.

China's lockdown had a profound impact on the global supply chain network, leading to disruptions in the availability of goods and components. As an automotive part supplier in Thailand, several operations management concepts can help navigate this situation. Supply chain diversification reduces reliance on a single source and enhances resilience. Demand forecasting enables efficient production planning. Cost optimization focuses on minimizing expenses without compromising quality. Supplier relationship management strengthens partnerships for better pricing and support. By implementing these concepts, the automotive part supplier can adapt to the challenges caused by China's lockdown and maintain a stable supply chain.

As a CEO of an SME in Thailand, taking action to generate more revenue and lower operational costs amidst increasing inflation and the cost of living is crucial. This can be achieved through strategies like market diversification to tap into new customer segments, product or service innovation to meet changing needs, efficient inventory management to minimize waste, streamlining processes to improve productivity, negotiating better deals with suppliers, and leveraging technology for automation and cost-saving measures. These actions help drive revenue growth and optimize operational expenses to maintain competitiveness in challenging economic conditions.

To know more about supply chain network, click here: brainly.com/question/32714336

#SPJ11

In general, how long does it take to accomplish a long-term goal?
A.
a few days to a week
B.
a few weeks to a month
C.
a few months to a year
D.
more than a year

Answers

The answer can change depending on the person and the goal. However, most long term goals will probably last for over a year.

Answer:

D

Explanation:

long term goals require time and planning.They are not something you can do this week or even this year.Long-Term goals usually take 12 months or more to achieve

For Tesla, the Model S represents a
(BCG) market growth/market share matrix.
on the Boston Consulting Group

Answers

The answer is "star" and its further explanation can be defined as follows:

The Tesla Model S is pleasant during the day, but fitness and finish are something to want. When heading for just a quick ring all-around city or heading off to the other side, Model S 2020 is full of space and luxury. It is a quality rating of 7 out of 10.The Tesla Model S is the top U.S. car with an overall score of 70 in the ultra-luxury car category. The top-range model S is 373 miles long and has one of today's largest ranges. For Tesla, Model S is a star in the growth/market share matrix of the Boston Consulting Group. The hunting for a high-quality premium car, Tesla Model S.Its overall design is maybe 10-years old, but the type S still sets a baseline for all EVs, and it has an unmatched driving range. The Model S is rather costly at $80,000 on the other hand.

That's why the correct answer is "star".

Learn more:

brainly.com/question/10803452


Which defines room and board?
O housing and meals that are often provided at additional cost
O monetary support that is used to help pay educational costs
O an educational institution or establishment, in particular one providing higher education
O a school that provides training in a specific skill or trade

Answers

Room and board are defined as educational institutions or establishments, particularly ones providing higher education. Thus the correct option is C.

What is the definition?

A definition of any word is a detailed description defining the accurate meaning to the reader in order to gain information and understand the meaning to utilize in vocabulary and used in any sentence.

Education and knowledge are not equivalent. Education is the means by which you acquire knowledge, which is what you already know. Knowledge is any truth or piece of information that you can retain and apply. We discover new things through education.

Therefore, option C is appropriate.

Learn more about Education, here:

https://brainly.com/question/29287243

#SPJ1

Personal Finance- Education and Training Costs Quick Check

1. Which defines room and board?

housing and meals that are often provided at additional cost

2. What is the definition of a college?

an educational institution or establishment, in particular one providing higher education

3. Which describes financial aid?

monetary support that is used to help pay educational costs

4. Which defines continuing education?

the formal classes that focus on a specific area of study, not usually taken for credit

5. What is post-secondary education?

the education level that follows the successful completion of high school

4/20/2023

A company is planning to migrate a business-critical dataset to Amazon S3. The current solution design uses a single S3 bucket in the us-east-1 Region with versioning enabled to store the dataset. The company's disaster recovery policy states that all data multiple AWS Regions. How should a solutions architect design the S3 solution

Answers

Incomplete question. Here are the options;

A. Create an additional S3 bucket in another Region and configure cross-Region replication.

B. Create an additional S3 bucket in another Region and configure cross-origin resource sharing (CORS).

C. Create an additional S3 bucket with versioning in another Region and configure cross-Region replication.

D. Create an additional S3 bucket with versioning in another Region and configure cross-origin resource (CORS).

Answer:

C. Create an additional S3 bucket with versioning in another Region and configure cross-Region replication.

Explanation:

Note that the Amazon S3 (Simple Storage Service) is an online cloud storage service that allows companies or developers to store and protect data, such as their website or mobile application data.

What this entails is that the solutions architect would design an additional S3 bucket that would support cross-region replication.

what is judiciary and executive?

Answers

Judiciary is the judicial authorities of a country; judges collectively.
Executive is the person or branch of a government responsible for putting policies or laws into effect.

types of waves that can be plane polarized


Answers

Plane polarisation is the method of allowing only waves orientated in the same direction - only allowing vibrations in one plane. Only transverse waves can be plane polarised because their vibration is perpendicular to the direction of energy travel - you can therefore have this vibration at different orientations

Which document determines the number of shares in a company? a stock prospectus an annual bill of rights a corporate charter an annual report

Answers

Answer: Corporate charter

Explanation:

The corporate charter is also referred to as the articles of incorporation. It is a document that contains the major components that make up a company, like the objectives of the company, the structure of the company, the number of shares the company has for sale and the planned operations of the company.

When a corporate charter is approved by the state, then the company will become a legal corporation. The corporate charter also contains the names of the people that are involved in its formation.

Answer:

The answer is (c) coporate charter

Explanation:

1. Which of the following is NOT a level of production? (A) Traditional production O(B) Domestic production O (C) Surplus production O (D) Extractive production * 1 point​

Answers

The correct answer is option (C) surplus production. Surplus production is not a level of production.

This is because surplus production is not a level of production, but rather a result of production. Surplus production refers to the amount of goods produced in excess of what is needed for immediate consumption or use. It is a surplus that can be stored or traded.
The other options, traditional production, domestic production, and extractive production, are all levels of production. Traditional production refers to the methods and techniques used by indigenous peoples to produce goods and services. Domestic production refers to the production of goods and services within a country's borders, while extractive production refers to the extraction of natural resources such as minerals, oil, and gas.
Understanding the different levels of production is important for policymakers and businesses as it helps them to make informed decisions about how to allocate resources and maximize production efficiency. It also helps to ensure that production is sustainable and does not harm the environment or deplete resources.

Therefore, the correct option is Options C. Surplus production is not a level of production.

for more such question on Surplus

https://brainly.com/question/15690421

#SPJ11

On September 3, 2018, Able, a single individual, purchased § 1244 stock in Red Corporation from his friend Al for $60,000. On December 31, 2018, the stock was worth $85,000. On August 15, 2019, Able was notified that the stock was worthless. How should Able report this item on his 2019 tax return?

Answers

He should ask them why it was worthless then after a while of thinking maybe have and idea on how to use it again

what should managers know about communication in the workplace

Answers

The things that managers should know about communication in the workplace is: Communication can help build strong relationships at workplace.

What is communication?

Communication can be defined as the way in which people tend to interact with one another. Communication can be inform of written or oral communication.

Effective communication is essential in a workplace based on the fact that it can help  people to build relationship at a workplace . Based on this the manager should know that effective communication can as well help to foster trust among employees.

Therefore effective communication is essential at workplace.

Learn more about  communication here:https://brainly.com/question/26152499

#SPJ1

a measurement scale that provides consistent results over time ___

Answers

A measurement scale that provides consistent results over time is called a reliable scale or measurement.

Reliability refers to the consistency and stability of measurements or scores obtained from a scale or instrument. In other words, if a measurement scale is reliable, it means that it produces consistent and reproducible results when used repeatedly or across different time points.

Reliability is an important characteristic of a measurement scale as it ensures that the instrument is dependable and can be trusted to provide consistent results. This allows researchers or practitioners to have confidence in the accuracy and stability of the measurements obtained, enabling them to draw meaningful conclusions or make reliable decisions based on the data collected. Various statistical methods and techniques are used to assess and evaluate the reliability of measurement scales, such as test-retest reliability, internal consistency reliability, inter-rater reliability, etc.

Learn more about reliable scale here:

https://brainly.com/question/32248259

#SPJ11

Why does the author introduce the text using a series of rhetorical questions?

A
to convince the reader that the majority of government power should be placed in the hands of the citizens, not the states that represent them

B
to inform the reader that the individual states need to maintain the bulk of power, instead of the federal government or the local communities in the state

C
to convince the reader that the majority of government power should be placed in the federal government because the states have too much infighting

D
to inform the reader that many of the individual states of the union are dissatisfied with the outcome of the conflict, and each of them are vying for power

Answers

Answer:

the answer is A. because we the citizen of a country vote them into power

Kay a person with a disability is an employee of mid state transport company when the firms elevator is taken out of service kay cannot get to her offics

Answers

Companies are supposed to provide working elevators for people living with disabilities.

In this regard, because Kay is disabled, the only means for her to access her office conveniently and on time is availability of elevator during the working hours.

However too, it could be inferred that the company is trying to kick her out if management is taking away the elevator or if they stopped the elevator officially from working.

What is an elevator?

An elevator is lift that moves people or passengers in a vertical shaft in a multistory building.

So therefore, companies are supposed to provide working elevators for people living with disabilities.

Learn more about elevators or lifts:

https://brainly.com/question/22048837

If u were signing papers and it asks u "does applicant identity as transgender" what would that mean?
Also what is a social security number?

Answers

Answer:

if u was a boy or a girl and turned in to a man and a boy turned into a girl

a bank card

1 transgender is where people change genders like a girl turns into a boy and it just the company asking you questions about yourself so they can prevent lawsuits and stuff

2 a social security number (SSN) is to basically verify that you live in the USA it come in numbers like 111,111,1111 you get it when you are born USA
I don’t know if other countries do this

Pls help me with this question!

Pls help me with this question!

Answers

The type of bank that contributes to the national economy by managing accounts and credit lines for both individuals and businesses is a commercial bank. So, the correct choice is option C.

Commercial banks are financial institutions that play a vital role in the economy by providing a wide range of banking services to individuals, businesses, and governments. They accept deposits from customers and offer various types of accounts, including checking accounts, savings accounts, and certificates of deposit. Commercial banks also provide loans and credit lines to individuals and businesses to support their financial needs.

By managing accounts, commercial banks facilitate the safekeeping of funds for individuals and businesses, allowing them to make transactions, earn interest on their deposits, and access their funds conveniently through various banking channels.

Furthermore, commercial banks contribute to the national economy by extending credit lines to individuals and businesses. These credit lines can be used for various purposes, such as financing investments, expanding businesses, purchasing assets, or managing cash flow. By providing credit, commercial banks support economic growth, entrepreneurship, and job creation.

In summary, commercial banks are the type of bank that actively contributes to the national economy by managing accounts and credit lines for both individuals and businesses, playing a crucial role in promoting financial stability and facilitating economic activities.

For more questions on economy

https://brainly.com/question/30131108

#SPJ8

Does having social responsibility make you viewed more or less favorable by consumers?

Answers

Answer:

Depends on the person but probably not

Explanation:

Jim paid $250,000 for an apartment building with a fair market value of $260,000. At the time of the sale, the building was appraised at $225,000. For income tax purposes, what would be the basis of the apartment building

Answers

The amount of $225,000 will be the would be the basis of the apartment building for income tax purposes.

Basically, the cost basis is the purchase cost which is $225,000.

The fair market value and appraised cost does not have anything to do with tax basis for income tax purposes.

In conclusion, the amount of $225,000 will be the would be the basis of the apartment building for income tax purposes

Read more about Cost basis

brainly.com/question/25899244

Calculate the range of potential annual returns if you invested 10% in bonds and 90% in stocks. How does this compare with the range of potential annual returns if you invested 10% in stocks and 90% bonds?

Answers

Answer:

From the graph, if you invest 10% in bonds and 90% in stocks,  the range of potential return is given as +49.8% to -39.0% with a average of 9.9% whereas if investment is  made by 10% in stocks and 90% in bonds, then the range of annual returns would become +31.2% to -8.2% with a average of 6%.  Therefore, as the investment in stocks increases the average annual returns also increase.

Explanation:

Hope this helps!

Which group was the originally intended focus of the amt?

Answers

The originally intended focus of the Alternative Minimum Tax (AMT) was high-income individuals or households who were taking advantage of various tax deductions and credits to significantly reduce their tax liability. The AMT was designed to ensure that these individuals or households pay a minimum amount of tax, regardless of their deductions and credits.


Here's a step-by-step explanation of how the AMT works:

1. When calculating regular income tax, individuals and households are allowed to claim deductions and credits to reduce their taxable income. This can include deductions for mortgage interest, state and local taxes, and charitable contributions, among others.

2. However, the AMT has a different set of rules and limits on deductions and credits. It disallows certain deductions and imposes a minimum tax rate on a broader range of income.

3. The AMT starts by calculating your taxable income using a different set of rules than regular income tax. It adds back certain deductions and exemptions that were allowed for regular tax purposes.

4. After calculating the AMT taxable income, the AMT applies a different set of tax rates, which are generally lower than regular tax rates, to determine the AMT liability.

5. Finally, the AMT liability is compared to the regular income tax liability. If the AMT liability is higher than the regular income tax liability, the individual or household must pay the higher AMT amount.

In summary, the originally intended focus of the AMT was high-income individuals or households who were using various tax deductions and credits to significantly reduce their tax liability. The AMT was designed to ensure that these individuals or households pay a minimum amount of tax by disallowing certain deductions and applying a different set of rules and rates for calculating the tax liability.

To know more about households visit-

https://brainly.com/question/12882354

#SPJ11

extracting round-dollar payments and summarizing them by vendor can help detect both corruption and billing schemes. True/False

Answers

The statement "extracting round-dollar payments and summarizing them by the vendor can help detect both corruption and billing schemes." is True

What are billing schemes?

Generally, Fraudulent billing practices target the company's payment processing infrastructure. According to the ACFE Report to the Nations, a billing scheme is "any scheme in which a person causes his employer to issue a payment by having to submit invoices for fictitious goods or services, inflated invoices, or invoices for personal purchases."

In other words, a billing scheme is "any scheme in which a person causes his employer to issue a payout by submitting receipts for personal purchases."

It is possible to uncover fraudulent billing schemes and improper business practices by "extracting round-dollar payments and summarizing them by the vendor." This statement is accurate.

Read more about billing schemes

https://brainly.com/question/22971866

#SPJ1

economic problem you face as an individual​

Answers

Answer:

I'm spending WAY too much money on my favorite snack which are purple Doritos. / The Dorito company is having a huge shortage of my favorite snack which are the purple Doritos and I don't know what to do!

Explanation:

Remember what economics is when you are asked this question. Economics basically are along the lines of distribution and consumption of goods could mean internationally or it could just mean in your state. If you have a favorite snack that you like to buy from stores whenever you go to them, you buying and taking that snack is basic economics, you have a demand for that product because you like it so much, and they (owners of the snack) have a supply of that demand so you then spend money (currency) in order to get that demand or snack which is basic economics. A problem in this scenario would be you spending too much money on your favorite snack, or the supplier of that snack is having a shortage and you can't buy your favorite snack as much as you want.

Hope this helps.

Answer:

The imbalance between production, distribution and consumption generates various phenomena that affect the economy; some of them are unemployment, shortages, overproduction, devaluation, inflation, indebtedness and damage to the environment.

Explanation:

Suppose that the true data-generating process includes an intercept along with the variables X2 and X3. Suppose that you inadvertently leave X3 out of your estimated model and only include an intercept and X2. Suppose further that X2 and X3 is positively correlated with Y, and X2 and X3 are negatively correlated with each other. As a result, the estimated coefficient on X2 (when X3 is omitted) is generally going to be:
unbiased.
too big.
too small,
leptokurtic.

Answers

When X3 is inadvertently left out of the estimated model and only an intercept and X2 are included, the estimated coefficient on X2 is generally going to be:

c. too big.

Leaving out X3, which is positively correlated with Y, leads to an omitted variable bias. This bias arises because X2 and X3 are negatively correlated with each other, and their effects on Y are confounded. By omitting X3, the estimated coefficient on X2 will capture the combined effect of X2 and the omitted variable X3. Since X3 is positively correlated with Y, this omission leads to an overestimation of the effect of X2 on Y, making the estimated coefficient on X2 "too big."

To know more about omission, visit

https://brainly.com/question/2681513

#SPJ11

What are interpersonal skills?
A.
the skills required to develop your personality
B.
the skills required to grow in your job role
C.
the overall way of portraying yourself when communicating with others
D.
the overall way you deal with conflicts

Answers

Answer:

The answer is 2

Explanation:

Answer is the letter D the overall way you deal ith conflicts

Answer:

C.

the overall way of portraying yourself when communicating with others

Explanation:

All of the following statements about public relations are true except group of answer choices because of its high cost, the use of pr has waned in recent years. consumers have become increasing skeptical of marketing claims made in conventional media. media coverage generated by pr is seen as more credible than paid advertising. public relations activities often support other promotional efforts. pr has become increasingly important as costs of other forms of marketing communications continue to increase.

Answers

All of the statements about public relations are true except for the first one, which states that the use of PR has waned in recent years because of its high cost.

In fact, public relations has become increasingly important as costs of other forms of marketing communications continue to increase. Public relations activities often support other promotional efforts and can be a cost-effective way to reach target audiences. Consumers have become more skeptical of marketing claims made in conventional media, which makes media coverage generated by PR more credible than paid advertising. Therefore, PR can be a valuable tool for building brand reputation and credibility.

To know more about public relations  visit:

https://brainly.com/question/20313749

#SPJ11

What is a benefit of sending Nissan-sponsored and third party automotive website links to customers?
A. They show you want to help them make an informed decision .
B. They can help you handle cross-shoppers
C. They give you a follow-up opportunity with prospects and be-backs

Answers

The benefit of sending Nissan-sponsored and third-party automotive website links to customers is that they provide a follow-up opportunity with prospects and be-backs. This option is represented by choice C.

By sharing these links, dealerships can stay engaged with potential customers and maintain communication throughout the buying process. The links can serve as helpful resources that provide additional information about Nissan vehicles, features, pricing, and comparisons with other models. This follow-up opportunity allows dealerships to nurture relationships with prospects, answer their questions, address concerns, and provide ongoing support.Sending Nissan-sponsored and third-party website links also demonstrates a willingness to help customers make informed decisions, as mentioned in choice A. It shows that the dealership values customer satisfaction and wants to provide them with comprehensive information to aid in their decision-making process.While choice B suggests that sending these links can help handle cross-shoppers (customers who are considering multiple brands), it is not specifically mentioned in the given options. However, it can be considered an additional benefit, as the website links can showcase Nissan's offerings and unique selling points, potentially influencing cross-shoppers to choose a Nissan vehicle.

In summary, sending Nissan-sponsored and third-party automotive website links to customers offers the benefits of providing follow-up opportunities, demonstrating a commitment to customer satisfaction, and potentially addressing the needs of cross-shoppers.

Learn more about customers: https://brainly.com/question/26313265

#SPJ11

Four year universities are the only type of school worth attending. True False​

Answers

Answer:

false

Explanation:

Answer:

false

Explanation:

there are a number of other reliable schooling options

Other Questions
Bio_U02_NGSQ1_FY21QuestiWhat is the difference between eukaryotic and prokaryotic cells?o Eukaryotic cells are found in bacteria and prokaryotic cells are not.O Prokaryotic cells are found in plants and animals and eukaryotic cells are notEukaryotic cells contain organelles and DNA enclosed within a nucleus and prokaryotic cells do not.Prokaryotic cells contain no organelles except DNA enclosed within a nucleus and eukaryotic cells do not For diatomic gas Cv = 5R/2 therefore for this gas what is the game? Carrie flew to toronto on a business trip. the purchase price of the ticket was $679 and it was bought from a travel agency on account. the entry to record the transaction is a) debit travel expense, $679; credit accounts payable, 8679. b) debit travel expense, $679; credit cash, 8679. c) debit capital, $679; credit accounts payable, $679. d) debit accounts payable, $679; credit travel expense, 8679. There is no erosion, other than surface creep and erosion due to impacts, on the Moon because there is no a. lava or flowing water. c. ejecta or lava. What are products sold at in pure competition? Intercellular communication involves a _____. a. signaling molecule and a signal-receiving chemical b. signaling molecule, a transducer molecule and a signal-receiving molecule c. transducer and a signaling molecule d. signaling molecule and a transducer molecule e. signaling molecule, a nerve net and a signal-receiving molecule which term describes a health promotion activity aimed at changing the behavior of a target audience? trace the pathway of blood from the aortic arch to the right anterior tibial artery How much would a 15.0kg object weigh on neptune if the acceleration due to gravity is 11.2? You have several suggestions for linking the app back to the customer service the bank provides and have shared those with your team. Whilst the feedback has been largely positive, one of your colleagues who joined HSBC more recently. Kieran, has pointed out a number of flows and shared some suggestions of his own How do you incorporate Kieran's feedback? Please RANK the responses from 1-5 by clicking and dragging the 3 Nines, with 1 being what you would most likely do and 5 being what you would least likely do 1. B. suggested fit in with what they were thinking. You want to make sure everyone feels listened to. 2. C. You proactively ask Kieran questions to gather detailed guidance on your suggestions. Whether the feedback is positive or negative, you are motivated to incorporate different perspectives. 3. D. You review your suggestions based on Kieran's feedback but make minor tweaks only. You prefer to prioritise feedback that has come from the wider team. 4. E. You rely mostly on the views of the majority. Given that Kieran has only recently joined, you trust that your wider team's expertise will be more reliable. 5. A. You send an email with Kieran's suggestions to the wider team to gather their thoughts. You prefer to wait for detailed feedback from the rest of the team before acting on Kieran's suggestions. assumptions: 15% discount rate calculate the following: a. annual roi (don't worry about tax consequences) b. total cost of ownership c. average annual cost of ownership d. net present value in year 3 e. payback period (Related to Checkpoint 9.2) (Yield to maturity) Hoyden Co's bonds mature in 15 years and pay 9 percent interest. annually. If you purchase the bonds for $1,200, what is their yield to maturity? The yield to maturity on the Hoyden bonds is \%. (Round to two decimal places.) (Related to Checkpoint 9.2) (Yield to maturity) Abner Corporation's bonds mature in 16 years and pay 9 percent interest annually. If you purchase the bonds for $1,250, what The Keynesian Transmission mechanism will eliminate a recessionary gap if there are not Liquidity Trap or Insensitive Investment function. Explain: a) What it is a liquidity trap b) What it is insensitive investment function 1. rocio strikes a 0.058-kg golf ball with a force of 272 n and gives it a velocity of 62.0 m/s. how long was rocio's club in contact with the ball? Probability diagram question..... The margin of error for a 95% confidence interval for the true mean mercury concentration in the Lower Willamette River is (rounded to five decimal digits) is O 0.02566 O 0.00199 O 0.00261 O none of the above Which of the following, if eliminated, would completely prevent the greenhouse effect from occurring on earth?Group of answer choicesa. Atmosphereb. Acid rainc. Fossil fuelsd. Clouds which describe the tempo of this excerpt and which do not? lullaby 1:41 describes the tempo walking pace press space to open lively press space to open vivace press space to open andante press space to open very slow If making a protein was like making a building, then the DNA molecule is like the blueprints and the RNA molecules are like the construction workersTrueFalse Discuss the importance and scope of business researchin Pakistan. What ethical issues involved in the business research.[04 Marks]