There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to: Multiple Choice 16. 64. 4. 2. 8.

Answers

Answer 1

Answer:

8

Step-by-step explanation:

Given that :

Number of activities = 4

Standard deviation of each activity = 4

Standard deviation of the critical path =?

To obtain the standard deviation of the critical path :

Take the square of each standard deviation:

Activity 1 = 4² = 16; activity 2 = 4² = 16 ; activity 3 = 4² = 16 ; activity 4 = 4² = 16

Sum of the squares :

16 + 16 + 16 + 16 = 64

Square root of the sum:

√64 = 8


Related Questions

the length of a rectangle is twice its width. if the perimeter of the rectangle is 54m find its area​

Answers

Answer:

You can denote the width of the rectangle as x,

than the length of the rectangle will be 2x

and the perimeter of the rectangle will be two length plus two width and it should be equal to 54 in

and the equation will look   2(2x)+2x=54

solving the equation 6x=54, x=9in

So the width of the  rectangle is 9in and the length is 9*2=18in

and the area of the rectangle is 9*18=162 sq in.

Are all intersecting lines perpendicular? Draw a picture to help explain your answer

Answers

Not all intersecting lines are perpendicular.

What are perpendicular lines?

Perpendicular lines require a 90-degree angle of intersection, creating the formation of right angles.

Nonetheless, unlike perpendicular lines that necessitate exactly 90 degrees of intersections, other types of driven lines can be at varying angles beside these.

As such, it is critical to highlight that in general intersecting lines come with different angles of intersection, and only those featuring exact 90-degree angle of intersection become normal cases of intersecting lines, becoming one among many subtypes existing today.

Learn more about perpendicular lines at

https://brainly.com/question/1202004

#SPJ1

Are all intersecting lines perpendicular? Draw a picture to help explain your answer

Find the equation of the parabola with the following properties. Express your answer in standard form.
Symmetric with respect to the line y = 2
Directrix is the line x = 11
P = -3

Answers

The  equation of the parabola with the following properties y = (-1/4)(x+3)^2 -1

What is the equation of the parabola?

To find the equation of a parabola, we can use the formula f(x) = ax^2 + bx + c, where a, b and c are congruent vertices.

Alternatively, we can use PF = PM to find the equation of the parabola.

vertex is half way between the focus and directrix

It's a downward opening parabola, general form

y= a(x-h)^2 + k

where (h,k) = vertex= (-3,-1)

plug in another point on the parabola to solve for a which gives

am answer with either x coefficient = -1'/4 or =4 Check the math.

one or the other is right another point is the y intercept = 9a-1

Another point is directly to the right of the focus  (-1, -2)  It's 2 down from the directrix and 2 to the right of the focus, equidistant.   plug that point into y= a(x+3)^2 -1 and solve for "a"  

-2 = a((-1+3)^2 -1

-2 = 4a -1

4a = -

a = -1/4

The parabola is y = (-1/4)(x+3)^2 -1

Learn more about the equation of the parabola on https://brainly.com/question/4074088

#SPJ1

Evaluate the expression, writing the result as a simplified complex number.

To earn full credit be sure to show all steps and calculations. You may wish to do the work on paper and submit an image of that written work.

\frac{(2+i)(4-2i)}{1+i}

Answers

The simplified expression involving complex numbers is given as follows:

5 + 5i.

What are complex numbers?

Complex numbers are number that have a real and an imaginary part, and are defined as follows:

z = a + bi.

In which:

a is the real part.b is the imaginary part.

The basic relation of complex numbers is given as follows:

i² = -1.

The fraction for this problem is given as follows:

(2 + i)(4 - 2i)/(1 + i).

The numerator is simplified as follows:

(2 + i)(4 - 2i) = 8 - 4i + 4i - 2i² = 8 + 2 = 10.

Hence the fraction is of:

10/(1 + i).

To remove the complex number from the denominator, the entire fraction is multiplied by the conjugate of the denominator, hence:

10/(1 + i) x (1 - i)/(1 - i) = 10(1 + i)/(1 - i²) = 10(i + 1)/2 = 5 + 5i.

More can be learned about complex numbers at https://brainly.com/question/10662770

#SPJ1

The table shows the average number of pounds of trash generated per person per day in the United States from 1970 to 2010. Use the statistics calculator to calculate the mean and median. Round the answers to the nearest hundredth

Answers

Answer:

Table needed to help

Step-by-step explanation:

Mean vs Median

The mean (informally, the “average“) is found by adding all of the numbers together and dividing by the number of items in the set: 10 + 10 + 20 + 40 + 70 / 5 = 30.

The median is found by ordering the set from lowest to highest and finding the exact middle. The median is just the middle number: 20.

If the point A (5,10) was reflected over the x-axis, what would the new coordinates
be?
O (9,2)
O (5,-10)
O (8,7)

Answers

The new coordinates wil be  (5,-10)

Plot (5, 10) on graph paper to understand. Imagine that point now reflecting or "flipping" over the x-axis. In this instance, it "flips the point down," moving the original point from the first quadrant to the fourth. The new y coordinate would be the "opposite" sign of the original but the x coordinate would remain unchanged. In light of this, the point is (5, -10)

The rule for reflection over the x-axis is

(x, y) → (x, - y)

Reflection over x-axis for (5,10) → (5,-10)

Coordinates are numerical lengths or angles that uniquely identify locations on two-dimensional (2D) surfaces or in three-dimensional (3D) space ( 3D ). Mathematicses, scientists, and engineers frequently employ a variety of coordinate systems.

Learn more about coordinate systems

https://brainly.com/question/4726772

#SPJ9

What is the correct decimal point placement for the product of 3.54 × 15.42? 54.5868 545.868 5458.68 54586.8

Answers

9514 1404 393

Answer:

  54.5868

Step-by-step explanation:

The multiplicands each have 2 digits to the right of the decimal point, so the product will have 2+2 = 4 digits to the right of the decimal point. The correct placement is ...

  54.5868

__

Another way to tell is that the product is in the neighborhood of 3·15 = 45, which is nowhere near 545 or 5458 or any higher value.

Answer: 54.5868

Since 3 x 15 is already 45, now we have to multiply the decimals, but we must put a point.

.54 x .42 = 9.5868

45 + 9.5868 = 54.5868.

Hope this helps!

What is the distance between -13 and 13

Answers

Answer:

26

Step-by-step explanation:

-13+13=0

0+13=13

13+13=26

HELP ME PLEASE!!!!!!
ZEARN!!!!

HELP ME PLEASE!!!!!!ZEARN!!!!

Answers

The expression 1 2/5 + 2 2/3 using fifteenths is 3 + 6/15 + 10/15

How to rewrite the expression using fifteenths

From the question, we have the following parameters that can be used in our computation:

1 2/5 + 2 2/3

3 + 2/5 + 2/3

To rewrite the expression using fifteenths, we multiply the numerator and the denominator of the fractions by the same number

In this case, we use 3 and 5

So, we have

3 + 2/5 * 3/3 + 2/3 * 5/5

Evaluate the products

3 + 6/15 + 10/15

Hence, the expression using fifteenths is 3 + 6/15 + 10/15

Read more about fraction at

https://brainly.com/question/31896427

#SPJ1

Differentiate the function h(x) using the quotient rule.
h(x) =2x+5 /2--x

Answers

\(h'(x)=\frac{\frac{d}{dx}[2x+5] (2-x)-\frac{d}{dx}[2-x](2x+5) }{(2-x)^2}\\=\frac{2(2-x)-(-1)(2x+5)}{(2-x)^2} \\=\frac{4-2x+2x+5}{(2-x)^2}\\=\frac{9}{(2-x)^2} \\=\frac{9}{x^2-4x+4}\)

Pythagorean TheoremFor the following right triangle, find the side length x. Round your answer to the nearest hundredth.18Х11

Pythagorean TheoremFor the following right triangle, find the side length x. Round your answer to the

Answers

Solution

For this case we can use the Pythagoras theorem and we have:

\(18^2=11^2+x^2\)

And solving for x we got:

\(x=\sqrt[]{18^2-11^2}=\sqrt[]{324-121}=\sqrt[]{203}=14.25\)

Then the answer is:

14.25

is 25 60 65 a right triangle

Answers

Answer:

No

Step-by-step explanation:

may i be marked as brainliest?

Answer:

Yes

Step-by-step explanation:

A triangle is right if its sides follow the Pythagorean triples.

We can simplify 25, 60, 65 by dividing by 5 for each number.

By doing this we get:

      5, 12, 13

If you memorized the Pythagorean triples, you can immediately know that 5, 12, 13 is one of them. Therefore, 25, 60, 65 is a right triangle.

you spin each spinner and find the sum how many different sums are possible​

you spin each spinner and find the sum how many different sums are possible

Answers

Answer:

let's use a sample set.

8+8, 8+4, 8+5, 8+6, 8+7

4+8, 4+4, 4+5, 4+6, 4+7

5+8, 5+4, 5+5, 5+6, 5+7

6+8, 6+4, 6+5, 6+6, 6+7

7+8, 7+4, 7+5, 7+6, 7+7

There is 25 sums.

Tim is 35 years old. He is 7 years younger than 6 times his daughter's age. The equation,
6x - 7 = 35, where x equals his daughter's age, can be used to find the age of Tim's daughter. How
old is Tim's daughter?
Choose the correct answer below.
OA. 7 years old
OB. 9 years old
OC. 4 years old
OD. 8 years old

Answers

Answer:

A. 7 years old

Step-by-step explanation:

6x-7=35 is the equation.

Add 7 to both sides, which gives you 6x=42.

Then both sides by 6, so 6/6=x and 42/6=7

So, x=7.

Since x is his daughter's age, x=7, so his daughter is 7.

6x-7≈35

or,6x=35+7

or,6x≈42

or,x=42÷6

x≈7

siete veces un número en expresión algebraica

Answers

In algebra, "seven times a number" is written as 7x, which is the multiplication of seven instances of the symbol x.

What is the formula for algebraic expressions?

An equation that includes constants, variables, and a few algebraic operations is said to be algebraic. A good example of an algebraic expression is 3x2 2xy + d. So, three different types of fundamental building blocks make up an algebraic expression: Coefficient (i.e. numbers) (i.e. numbers)

A seven-times-a-number is represented by multiplying it by seven or adding it to another integer (since this is an abbreviated successive addition ).

If x is any number, then it may be written as follows seven times: Algebraic expressions (numbers or letters) are linked by fundamental operations including addition, subtraction, multiplication, and division in mathematical language.

To learn more about algebraic expression from given link

https://brainly.com/question/4541471

#SPJ1

Complete question -

Seven times a number in algebraic expression

1. Scale 1 cm = 250 km
25
Using the scale above, calculate to find how
many km are in the following map distances:
a.) 2 cm =
km
b.) 5 cm
km
c.) 3 cm=
km

Answers

Answer:

a= 500km b= 1,250 c= 750

Step-by-step explanation:

a= 250x2=500km

b= 250x5=1,250km

c= 250x3=750km

Write the equation of the line in slope-intercept form. The coefficients in the equation are b=4 and m=-5

Answers

Answer:

y = -5x + 4

Step-by-step explanation:

Slope-intercept form of the equation is:

y = mx + b

In the question, we are given m = -5 and b = 4.

Fill in the numbers for m and b.

The m tells you how steep the line is (the slope) And b tells you where the line crosses the y-axis (y-intercept).

Translate into a proportion: What number is 63% of 107? Let n= the number.

Answers

Answer:

look at the picture.......................

Translate into a proportion: What number is 63% of 107? Let n= the number.

Rectangles abcd and klmn are similar. If their permitted are 20 and 16, and the area of the larger rectangle is 25, what is the area of the smaller rectangle?

Answers

The area of the smaller rectangle (KLMN) is 16.

Since rectangles ABCD and KLMN are similar, their corresponding sides are proportional.

Let's assume the length of side AB in rectangle ABCD is x, and the length of side KL in rectangle KLMN is y.

We can set up the proportion:

(x/y) = (20/16)

To find the area of the smaller rectangle, we need to determine the ratio of their areas.

Since the area of a rectangle is given by the product of its length and width, the ratio of the areas will be equal to the square of the ratio of their sides:

(Area of ABCD)/(Area of KLMN) = (x²)/(y²)

We are given that the area of ABCD is 25, so we have:

25/(Area of KLMN) = (x²)/(y²)

To find the area of KLMN, we need to substitute the values of x and y from the proportion:

25/(Area of KLMN) = (20/16)²

Simplifying the right side:

25/(Area of KLMN) = (5/4)²

25/(Area of KLMN) = 25/16

Cross-multiplying:

25 × 16 = 25 × (Area of KLMN)

400 = 25 × (Area of KLMN)

Dividing both sides by 25:

16 = Area of KLMN

Therefore, the area of the smaller rectangle (KLMN) is 16.

Learn more about similarity click;

https://brainly.com/question/26451866

#SPJ1

What is the slope of the line whose equation is 2y=3x+4

Answers

Answer:

3/2

Step-by-step explanation:

use the slope-intercept formula y=mx+b to find the slope

hope this helped♥

Answer:

3/2

Step-by-step explanation:

If you divide both sides by 2 to convert to y=mx+b, you get y=3/2x+2. M is the slope, which means that the slope is 3/2.

(1, 72), (3,66), (5, 53), (7, 40), (9, 34)
WILL MARK BRAINLIEST Cole determined the equation of a linear regression line, and determined that these are the corresponding predicted v
(1, 74), (3,63), (5, 52), (7, 41), (9, 30)
Use the point tool to graph the residual plot for the given values in the data set.

Answers

Answer:

y = \(-\frac{11}{2}\) x + \(\frac{159}{2}\)

Step-by-step explanation:

(1, 74)

(3, 63)

m = (63 - 74) / (3 - 1) = \(-\frac{11}{2}\)

y - 74 = \(-\frac{11}{2}\) (x - 1)

y = \(-\frac{11}{2}\) x + \(\frac{159}{2}\)

(1, 72), (3,66), (5, 53), (7, 40), (9, 34)WILL MARK BRAINLIEST Cole determined the equation of a linear

The factors of 16-y² are​

Answers

Answer:

(4 + y)(4 - y)

Step-by-step explanation:

\(16 - {y}^{2} \\ \\ = {4}^{2} - {y}^{2} \\ \\ = (4 + y)(4 - y)\)

A taste test asks people from Texas and California which pasta they prefer, brand A or brand B. This table shows the results,​

A taste test asks people from Texas and California which pasta they prefer, brand A or brand B. This

Answers

Answer:

D. 0.53

Step-by-step explanation:

California = 90

Total of those who prefer Brand A = 170

To find the percentage, you do:

90/170 × 100 = 52.941...

However you have to round it to two decimal points, hence you do:

52.941 ≈ 53%

53% = 0.53

This is due to 53% representing 53/100 = 0.53

Therefore, the probability that the person that likes brand A is from California is 0.53

:)

1/4×10/12 simplest form

Answers

Answer:

10/48 - 2/24 - 1/12

Step-by-step explanation:

answer is 1/12

(50 POINTS AND BRAINLYEST)
Please answer them all :)


A dilation that makes a shape larger is a(n)....

Question 4 options:

expansion


contraction


reflection


rotation

Question 5 (1 point)
Saved
A dilation that makes a shape smaller is a(n)....

Question 5 options:

expansion


contraction


reflection


rotation

Question 6 (1 point)
The resulting shape after a transformation is completed is called the...

Question 6 options:

final shape


pre-image


image


result

Question 7 (1 point)
The number that is used to determine if a dilated shape has been expanded or contracted is the...

Question 7 options:

scale factor


center of dilation


origin


really important number

Answers

Question 4: ExpansionQuestion 5: ContractionQuestion 6: ImageQuestion 7: Scale factor

Joseph Selects a card from a standard deck of 52 cards and then replaces it afterwards he decides to record the total number of red cards that he selects and calculates the proportion of red cards that he has selected so far after each pick he then constructs a graph to visualize his results

Answers

The answer to the given question is Option B.

Probability means possibility. A branch of mathematics that deals with the occurrence of  random events.

Probability is a measure of the likelihood of an event occurring. Many events cannot be predicted with absolute certainty.

We can only predict  the probability that an event will occur. H. Possibility of using it. Probabilities can range  from 0 to 1. 0 means the event is not possible, 1 indicates the specific event.  

For example, if you toss a coin, you get either heads or tails. There are only two possible outcomes  (H, T). But if you toss two coins in the air,  three  events can occur, such as ), (T, T).

Probability of an event occurring P(E) = number of favorable outcomes/total number of outcomes.

At no point can we distinguish between diamonds and hearts, as we are only interested in finding red cards. as a result,

The wrong statement is:

For a given number of selections, we can use Joseph's graph to find the number of diamonds that he has picked so far.  

Therefore, the ultimate answer to the given question is Option B.

Learn more about probability here

https://brainly.com/question/24756209

#SPJ9

The question is incorrect, The correct question is

Joseph selects a card from a standard deck of 52 cards and then replaces it afterwards. He decides to record the total number of red cards that he selects and calculates the proportion of red cards that he has selected so far after each pick. He then constructs a graph to visualize his results. Which of the following statements is FALSE?

A. The theoretical probability for selecting a red card in each pick is 0.5.

B. For a given number of selections, we can use Joseph's graph to find the number of diamonds that he has picked so far.

C. This is an example of the law of large numbers.

D. The relative frequency of selecting a red card changes with the increase in number of selections.

Bakeware, a bake, ware production company, has a production cost of $6 per round cake pan. Each round cake pan sells for $15. Bakeware's monthly fixed cost is $180,000.
A. Find the break-even quantity.
B. Find the break-even revenue.
C. Find the break-even point.
D. If the company produces and sells 15,000 pans, will this result in a profit or a loss?
E. If the company produces and sells 28,000 pans, will this result in a profit or a loss?

Answers

Answer:

your cheating

Step-by-step explanation:

stopppp

What is the perimeter of the rectangle in the coordinate plane? y 36 units 15 147 38 units 13+ 12+ 65 units 117 O 70 units ​

What is the perimeter of the rectangle in the coordinate plane? y 36 units 15 147 38 units 13+ 12+ 65

Answers

Answer:

38 units

Step-by-step explanation:

14 * 2 = 28

5 * 2 = 10

28 + 10 = 38

Mark me as brainliest, I am trying to level up.

What fraction is not greater than 1/2? 7/8 4/6 3/5 2/5

Answers

Answer:this is so ez

Step-by-step explanation: 2/5

PLZ HELP ASPPP PLZ I will mark your answer as brainlist

PLZ HELP ASPPP PLZ I will mark your answer as brainlist

Answers

Answer:

a(-2,4) b(-4,2) c(-8,6) d(-6,8) these should be the answers

Other Questions
A nurse is caring for a neonate with a suspected diaphragmatic hernia. The nurse should question an order fora) mask ventilation.b) chest x-ray.c) immediate endotracheal intubation.d) placement of an orogastric tube. Have the topic be Animal shelter pleaseI NEED THIS DONE ASAP what level of anxiety has heightened sensory awareness, leading to seeing, hearing, and grasping more information?*** Should We Tax Pizza and Soda to Reduce the Obesity Epidemic?Read the research paper FOOD PRICE DIET AND HEALTH.pdf Download FOOD PRICE DIET AND HEALTH.pdfReflecting back on Chapter 18, what is significant about lower weight and improved HOMA_IR* Score? (2 pts)Do YOU think foods such as soda and pizza should be taxed in an attempt to deter people from eating them as a way to tackle the high rate of obesity and diabetes? Explain your answer.3. Do you think the size and selection of participants were positive or negative to the results of the study? Explain. (2 pts) Reference: Chapter 1.3 The Science of Nutrition Mariah will not consider shopping at a nearby farmer's market based on negative comments made by her parents; in other words, she has developed a negative attitude toward this specific farmer's market.a.Trueb.False How did Pericles help rebuild Athens after the Greco-Persian wars? Funny responses for who do you like Services high in ________ qualities are those services that have characteristics that the buyer normally finds hard to evaluate even after consumption. the ______ with china increased from $1.6 billion to $28.3 billion in july 2020. this means that imports from china exceed exports to china from the united states. Edgar can sound out most three-letter words, but when he sees a long eight-letter word, he turns to his teacher instead of trying to sound it out. His teacher encourages him to go ahead and try to sound it out by breaking it down into two parts. According to Vygotsky, Edgar:______.a. is in the zone of proximal development. b. is engaged in egocentric speech. c. is developing his fast-mapping skills. d. needs to practice his language overregularization What is the equation of a line having a slope of 5 and whose y-intercept is 8? Areas of the ________ and hindbrain have an important role to play in regulating eating and hunger. what's the correct answer 2(k + 1) = -4(k - 2) Conduct the hypothesis test and provide the test? statistic, critical value and? P-value, and state the conclusion. A person drilled a hole in a die and filled it with a lead? weight, then proceeded to roll it 200200 times. Here are the observed frequencies for the outcomes of? 1, 2,? 3, 4,? 5, and? 6, respectively: 26?, 31?, 43?, 39?, 29?, 32. Use a 0.10significance level to test the claim that the outcomes are not equally likely. Does it appear that the loaded die behaves differently than a fair? die? (if you have a graphing calculator can you please tell me how to do it there) Soledad studied rocks and how they help show the history of Earth. She knew that scientists use different ways to find out how old rock layers are and recognized one such example in the rock in the image. The image is an example of a/an _________________ rock. Which sentence is written from the third person point of view? (5 points)It seemed like it rained almost every day of our spring vacation.The weather refused to cooperate during my vacation.The weather should have been beautiful during spring vacation.I was disappointed that it rained so much on our vacation. select the correct answer what is the left hand limit of g(x)=[tex] \frac{ {x}^{2} - 25 }{x - 5} [/tex]as x aproaches 5 Last year Martin Motors reported the following income statement:sales of $12,000,000, cost of goods sold 60% of sales, interest expense of $500,000, preferred stock dividend of $200,000, common stock dividend of $650,000, depreciation of $2,000,000, and other administrative expense of $800,000. In addition, capital expenditures were $4,000,000 and net operating working capital increased by $2,200,000. The tax rate was 40%.Find operating income for last year. What is another name for operating income?Find free cash flow for last year. -i need your help pleas know